21 Aug 2026, 10:57 PM
Pratik · PPR-2026-08-00148
Step updates
LS Material Delivery · DoneMarking · DoneCivil Opening · DoneSupport · DoneCopper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Doneodu unit installation · DoneFinal Nitrogen Testing · DoneFINAL RA Measurement Received · DoneDisk Valve · Not requiredFan Installation · Not requiredGrill Installation · Not requiredODU Dismental · Not requiredIDU Dismental · Not requiredFresh Air - PVC PIPE / Duct · Not requiredCollar · Not requiredMain Ducting · Not requiredMain Ducting Dismental · Not requiredDrain Dismental · Not requiredCopper Piping Dismental · Not requiredUnderdake Insulation · Not required
ActivityCommissining completed today.
Tomorrow's plan- · starts 22 Aug 2026