Report History
Review every submitted site visit, current project steps, holds, completion times, and upcoming plans.
100 reports shown
Tushar kale-test
Done
PPR-2026-09-00233
1 done done
Tomorrow: Planned for tomorrow: Copper Piping Dismental.
Hemant Dhoka Residence
—
PPR-2026-09-00232
done
Tomorrow: No plan
Suyog Navkar › Kalpa › 1701
Done
PPR-2026-09-00231
13 done done
Tomorrow: -
Rachana Developer - Kalbhor Residence
Open
PPR-2026-09-00230
1 open done
Tomorrow: Planned for tomorrow: Fresh Air - PVC PIPE / Duct. Nothing
PINNACLE MOBILITY SOLUTIONS PVT LTD(Ground Floor, Chimbali)
Done
PPR-2026-09-00229
4 done done
Tomorrow: All work completed
ULTRA CORPOTECH PVT. LTD -Unit 701
—
PPR-2026-09-00228
done
Tomorrow: -
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-09-00227
done
Tomorrow: -
RENOLIT India Pvt. Ltd
Open
PPR-2026-09-00226
1 open done
Tomorrow: Planned for tomorrow: Indoor Installation. Ground floor machines installation will be done if will get clearance, as there is painting pending
Kalashetram Silk And Sarees(Ground Floor & First Floor)
—
PPR-2026-09-00225
done
Tomorrow: Ground floor balance work started
Kaveri Mulay VRV
Done
PPR-2026-09-00224
7 done done
Tomorrow: No plan
RENOLIT India Pvt. Ltd
Open
PPR-2026-09-00223
1 open done
Tomorrow: Planned for tomorrow: Indoor Installation. Indoor units connection will be done which is installed
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
—
PPR-2026-09-00222
done
Tomorrow: Sunday
Suyog Navkar › Kalpa › 1402
Done
PPR-2026-09-00221
1 done done
Tomorrow: Sunday
Ultra Unit - 6 Production Office (Ground Floor)
Done
PPR-2026-09-00220
1 done done
Tomorrow: Sunday
Ruikar House
Open
PPR-2026-09-00219
1 open done
Tomorrow: Nothing
Kaveri Mulay VRV
Done
PPR-2026-09-00218
1 done done
Tomorrow: Planned for tomorrow: Copper Piping.
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
Done
PPR-2026-09-00217
6 done done
Tomorrow: -
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-09-00216
done
Tomorrow: Planned for tomorrow: Fresh Air - PVC PIPE / Duct.
Rachana Developer - Kalbhor Residence
Open
PPR-2026-09-00215
1 open done
Tomorrow: Planned for tomorrow: Fresh Air - PVC PIPE / Duct. Toilet ventilation PVC piping work will be continued
PINNACLE MOBILITY SOLUTIONS PVT LTD(Ground Floor, Chimbali)
Open
PPR-2026-09-00214
3 open done
Tomorrow: Nothing
Suyog Navkar › Kalpa › 2101
Done
PPR-2026-09-00213
1 done done
Tomorrow: -
Suyog Navkar › Kalpa › 2001
Done
PPR-2026-09-00212
1 done done
Tomorrow: -
Rahul Rathi Residence
Open
PPR-2026-09-00211
2 open done
Tomorrow: Nothing
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-09-00210
done
Tomorrow: -
Hind Sadi Center
Not Required
PPR-2026-09-00209
done
Tomorrow: Odu Unit shifting work
Kalashetram Silk And Sarees(Ground Floor & First Floor)
Done
PPR-2026-09-00208
3 done done
Tomorrow: No plan
Ultra Unit - 6 Production Office ( First Floor)
Done
PPR-2026-09-00207
1 done partial
Tomorrow: -
RENOLIT India Pvt. Ltd
Open
PPR-2026-09-00206
2 open done
Tomorrow: Planned for tomorrow: Fresh Air - PVC PIPE / Duct.
Clover Pinnacle Ridge
Open
PPR-2026-09-00205
7 open done
Tomorrow: Plan
Hemant Dhoka Residence
Done
PPR-2026-09-00204
1 done done
Tomorrow: Odu Unit shifting work
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
Done
PPR-2026-09-00203
2 done done
Tomorrow: -
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-09-00202
done
Tomorrow: Sunday
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
—
PPR-2026-09-00201
done
Tomorrow: Planned for tomorrow: Indoor Installation.
Suyog Navkar › Kalpa › 1502
Done
PPR-2026-09-00200
1 done done
Tomorrow: -
Ultra Unit - 6 Production Office (Ground Floor)
Done
PPR-2026-09-00199
1 done done
Tomorrow: -
Ultra Unit - 6 Production Office ( First Floor)
Done
PPR-2026-09-00198
1 done partial
Tomorrow: -
Kalashetram Silk And Sarees(Ground Floor & First Floor)
Done
PPR-2026-09-00197
3 done done
Tomorrow: No
Tushar Patil office
Done
PPR-2026-09-00196
2 done done
Tomorrow: Planned for tomorrow: Disk Valve. Nothing
Rachana Developer - Kalbhor Residence
Open
PPR-2026-09-00195
1 open done
Tomorrow: Planned for tomorrow: Indoor Installation. Nothing
Ultra Unit - 6 Production Office (Ground Floor)
Not Required
PPR-2026-09-00194
done
Tomorrow: -
Ultra Unit - 6 Production Office ( First Floor)
Done
PPR-2026-09-00193
4 done partial
Tomorrow: -
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
Done
PPR-2026-09-00192
1 done done
Tomorrow: Fabrication
Ravet Showroom(CHANDUKAKA SARAF)
Open
PPR-2026-09-00191
2 open partial
Tomorrow: Planned for tomorrow: Copper Piping, Drain. Split AC copper and drain piping
Pankaj Runwal Residence
Done
PPR-2026-09-00190
1 done failed
Tomorrow: No plan
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
Done
PPR-2026-09-00189
1 done done
Tomorrow: Planned for tomorrow: Copper Piping.
Yashwant Bodke Residence
Done
PPR-2026-09-00188
1 done done
Tomorrow: -
Kasturi › Balmoral TowerD-wing › D-102
Done
PPR-2026-09-00187
7 done partial
Tomorrow: Work on going
Ravet Showroom(CHANDUKAKA SARAF)
Open
PPR-2026-09-00186
1 open partial
Tomorrow: Planned for tomorrow: Indoor Installation, Drain, Copper Piping. Copper and drain piping connection of installed machines
RENOLIT India Pvt. Ltd
Open
PPR-2026-09-00185
3 open failed
Tomorrow: Planned for tomorrow: LS Pressure Testing, Fan Installation.
Chandukaka Saraf - Palus
Done
PPR-2026-09-00184
2 done done
Tomorrow: Odu Unit installation
Pankaj Runwal Residence
Done
PPR-2026-09-00183
1 done done
Tomorrow: Meeting attend at site with Anil sir
Sachin Wani's residence
Done
PPR-2026-09-00182
1 done done
Tomorrow: Planned for tomorrow: Commissining.
Yashwant Bodke Residence
Done
PPR-2026-09-00181
10 done done
Tomorrow: Planned for tomorrow: Commissining.
Rama Equator office no. 912 (PCMC)
Done
PPR-2026-09-00180
1 done done
Tomorrow: Nothing
Suyog Navkar › Kalpa › 101
—
PPR-2026-08-00179
done
Tomorrow: -
Avian Valley, Bhugaon
—
PPR-2026-08-00178
done
Tomorrow: -
Kalashetram Silk And Sarees(Ground Floor & First Floor)
Done
PPR-2026-08-00177
2 done done
Tomorrow: Out side tray installation work
Rama Equator office no. 912 (PCMC)
Done
PPR-2026-08-00176
3 done done
Tomorrow: Planned for tomorrow: Commissining. Nothing
Avian Valley, Bhugaon
Done
PPR-2026-08-00175
22 done done
Tomorrow: Sunday
Ravet Showroom(CHANDUKAKA SARAF)
Done
PPR-2026-08-00174
1 done partial
Tomorrow: Sunday
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-08-00173
done
Tomorrow: Sunday
PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)
Done
PPR-2026-08-00172
3 done done
Tomorrow: Sunday.
Rama Equator office no. 912 (PCMC)
Open
PPR-2026-08-00171
3 open done
Tomorrow: Outdoor unit connection and Final Nitrogen pressure testing
Rama Equator office no. 912 (PCMC)
Open
PPR-2026-08-00170
1 open done
Tomorrow: Planned for tomorrow: Copper Piping. Odu shaft piping and connection
Kalashetram Silk And Sarees(Ground Floor & First Floor)
—
PPR-2026-08-00169
failed
Tomorrow: Remote
Ultra Unit - 6 Production Office ( First Floor)
Not Required
PPR-2026-08-00168
partial
Tomorrow: Drain piping.
Hotel Paradise Chakan
Done
PPR-2026-08-00167
3 done done
Tomorrow: Pressure testing.
Suyog Navkar › Kalpa › 1602
Done
PPR-2026-08-00166
17 done done
Tomorrow: -
Rama Equator office no. 912 (PCMC)
Open
PPR-2026-08-00165
4 open done
Tomorrow: Planned for tomorrow: Indoor Installation, Copper Piping, Cable, Drain. Vertical piping work
Serview Enterprises Akurdi Office
Open
PPR-2026-08-00164
2 open done
Tomorrow: Planned for tomorrow: Support. Copper pipe brazing work
Pankaj Runwal Residence
Done
PPR-2026-08-00163
1 done done
Tomorrow: No Plan
Suyog Navkar › Kalpa › 702
Done
PPR-2026-08-00162
17 done done
Tomorrow: -
Hotel Paradise Chakan
—
PPR-2026-08-00161
done
Tomorrow: ODU installation.
Ultra Unit - 6 Production Office (Ground Floor)
Done
PPR-2026-08-00160
11 done done
Tomorrow: Copper piping.
Pankaj Runwal Residence
—
PPR-2026-08-00159
done
Tomorrow: Odu Unit shifting & Copper pipe conection work
Suyog Navkar › Kalpa
Done
PPR-2026-08-00158
2 flats
401
1101
1 done done
Tomorrow: -
Serview Enterprises Akurdi Office
Open
PPR-2026-08-00157
2 open done
Tomorrow: Planned for tomorrow: Copper Piping, Support. Copper piping work will be started
Pankaj Runwal Residence
Done
PPR-2026-08-00156
2 done done
Tomorrow: Odu Unit shifting & Ducting Collar installation.
Kasturi › Balmoral TowerD-wing
Done
PPR-2026-08-00155
2 flats
D -2301
2303
27 done partial
Tomorrow: Disk valve installation work on going
Hind Sadi Center
Done
PPR-2026-08-00154
8 done done
Tomorrow: No plan
Tushar Patil office
Open
PPR-2026-08-00153
2 open done
Tomorrow: Planned for tomorrow: Indoor Installation, IDU/ODU Pressure Testing, Final Nitrogen Testing.
RENOLIT India Pvt. Ltd
Open
PPR-2026-08-00152
3 open done
Tomorrow: Planned for tomorrow: Drain, Cable, Fan Installation. Nothing
PMStest
Done
PPR-2026-08-00151
1 done done
Tomorrow: Nothing
Prakash Karia-A-602 Verde Residence
—
PPR-2026-08-00150
done
Tomorrow: nothing its test
Ultra Unit - 6 Production Office ( First Floor)
Not Required
PPR-2026-08-00149
partial
Tomorrow: Copper piping.
Suyog Navkar › Kalpa
Done
PPR-2026-08-00148
3 flats
1802
1001
1901
51 done done
Tomorrow: -
Darshana Industries Phulgaon Plant
Open
PPR-2026-08-00147
1 open done
Tomorrow: No plan tomorrow
RENOLIT India Pvt. Ltd
Open
PPR-2026-08-00146
1 open done
Tomorrow: Planned for tomorrow: Drain, Cable. Humidifier and Dehumidifier-marking
Hemant Dhoka Residence
Done
PPR-2026-08-00145
1 done done
Tomorrow: No plan
Vansum Industries -Pune IT Park A building 101 -104
Done
PPR-2026-08-00144
3 done done
Tomorrow: Planned for tomorrow: Indoor Installation.
Hotel Paradise Chakan
Done
PPR-2026-08-00143
1 done done
Tomorrow: Tomorrow no clearance for work.
Ultra Unit - 6 Production Office ( First Floor)
Done
PPR-2026-08-00142
1 done partial
Tomorrow: Planned for tomorrow: Copper Piping.
Bajaj Auto Limited
Done
PPR-2026-08-00141
1 done done
Tomorrow: Planned for tomorrow: Pre-Commissining. Wiring and panel installation
Ruikar House
Open
PPR-2026-08-00140
2 open done
Tomorrow: Planned for tomorrow: Drain, Copper Piping.
Ultra Unit - 6 Production Office (Ground Floor)
—
PPR-2026-08-00139
done
Tomorrow: Planned for tomorrow: Copper Piping.
Suyog Navkar › Shruta › 2001
Done
PPR-2026-08-00138
12 done done
Tomorrow: Planned for tomorrow: odu unit installation.
Hotel Paradise Chakan
Done
PPR-2026-08-00137
3 done done
Tomorrow: Planned for tomorrow: odu unit installation.
Kasturi › Balmoral River side D-wing
Done
PPR-2026-08-00136
2 flats
D-2401
D-2402
22 done partial
Tomorrow: Final pressure hold work on going
Kalashetram Silk And Sarees(Ground Floor & First Floor)
Done
PPR-2026-08-00135
7 done done
Tomorrow: No plan
Clover Pinnacle Ridge
Done
PPR-2026-08-00134
2 done done
Tomorrow: No Plan