Kasturi › Balmoral River side D-wing › D-2402

PPR-2026-08-00136 · 19 Aug 2026, 07:05 PM · flat 2 of 2
Done
2 flats in this visit — pick one: D-2401 D-2402
EngineerShubham
Site typeVRV · Developer
People on site2
ActivityD building 2401,2402 flats outdoor connection work complete
Tomorrow's planFina pressure hold work on going
Next step date

Current project steps

10 tracked
LS Material Delivery
Done
19 Aug 2026, 07:05 PM · Shubham
Marking
Done
19 Aug 2026, 07:05 PM · Shubham
Civil Opening
Done
19 Aug 2026, 07:05 PM · Shubham
Support
Done
19 Aug 2026, 07:05 PM · Shubham
Copper Piping
Done
19 Aug 2026, 07:05 PM · Shubham
Cable
Done
19 Aug 2026, 07:05 PM · Shubham
Drain
Done
19 Aug 2026, 07:05 PM · Shubham
HS Material Delivery IDU
Done
19 Aug 2026, 07:05 PM · Shubham
HS Material Delivery ODU
Done
19 Aug 2026, 07:05 PM · Shubham
Indoor Installation
Done
19 Aug 2026, 07:05 PM · Shubham

Complete visit timeline

1 visit
19 Aug 2026, 07:05 PM
Shubham · PPR-2026-08-00136
Step updates
LS Material Delivery · DoneMarking · DoneCivil Opening · DoneSupport · DoneCopper Piping · DoneCable · DoneDrain · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Done
ActivityOutdoor connection work complete
Tomorrow's planFinal pressure hold work on going

Photos and files

3 attachments

Report processing

partial
photo save
done
19 Aug 2026, 07:06 PM
2 photo(s) uploaded across 2 flat(s)
sheet write
done
19 Aug 2026, 07:06 PM
2 row(s) written
pms update
done
19 Aug 2026, 07:06 PM
PMS row stamped
pdf
done
19 Aug 2026, 07:06 PM
PDF built
email
done
19 Aug 2026, 07:10 PM
emailed
whatsapp
failed
19 Aug 2026, 07:10 PM
no client number