Marking
Done
11 Aug 2026, 09:56 PM · Pratik
Support
Done
12 Aug 2026, 06:52 PM · Pratik
Copper Piping
Done
26 Aug 2026, 10:48 PM · Pratik
Cable
Done
26 Aug 2026, 10:48 PM · Pratik
Drain
Done
26 Aug 2026, 10:48 PM · Pratik
LS Pressure Testing
Done
26 Aug 2026, 10:48 PM · Pratik
IDU/ODU Pressure Testing
Done
26 Aug 2026, 10:48 PM · Pratik
1st RA Measurement Submitted by PE
Done
26 Aug 2026, 10:48 PM · Pratik
HS Material Delivery IDU
Done
26 Aug 2026, 10:48 PM · Pratik
HS Material Delivery ODU
Done
26 Aug 2026, 10:48 PM · Pratik
Indoor Installation
Done
26 Aug 2026, 10:48 PM · Pratik
odu unit installation
Done
26 Aug 2026, 10:48 PM · Pratik
Final Nitrogen Testing
Done
26 Aug 2026, 10:48 PM · Pratik
Underdake Insulation
Not required
03 Sep 2026, 11:57 PM · Pratik
Copper Piping Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Drain Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
IDU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
ODU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting
Done
04 Sep 2026, 11:25 PM · Pratik
Fresh Air - PVC PIPE / Duct
Done
12 Sep 2026, 10:49 PM · Pratik