Kalashetram Silk And Sarees(Ground Floor & First Floor)

PPR-2026-10-00353 · 27 Oct 2026, 01:42 PM
Done
EngineerDada
Site typeVRV · General
People on site1
ActivityCable tray cover installation done.
Tomorrow's planNo
Next step date—

Current project steps

18 tracked
Civil Opening
Done
19 Aug 2026, 01:11 PM · Dada
Support
Done
19 Aug 2026, 01:11 PM · Dada
Copper Piping
Done
19 Aug 2026, 01:11 PM · Dada
Cable
Done
19 Aug 2026, 01:11 PM · Dada
Drain
Done
19 Aug 2026, 01:11 PM · Dada
LS Pressure Testing
Done
19 Aug 2026, 01:11 PM · Dada
Fresh Air - PVC PIPE / Duct
Done
19 Aug 2026, 01:11 PM · Dada
Marking
Done
31 Aug 2026, 09:26 PM · Dada
odu unit installation
Done
27 Oct 2026, 01:42 PM · Dada
HS Material Delivery IDU
Done
04 Sep 2026, 09:36 PM · Dada
HS Material Delivery ODU
Done
04 Sep 2026, 09:36 PM · Dada
Indoor Installation
Done
04 Sep 2026, 09:36 PM · Dada
IDU/ODU Pressure Testing
Done
09 Sep 2026, 03:01 PM · Dada
Final Nitrogen Testing
Done
09 Sep 2026, 03:01 PM · Dada
Grill Installation
Done
29 Sep 2026, 05:52 PM · Jay Bhosale
LS Material Delivery
Done
08 Oct 2026, 09:13 PM · Dada
Fan Installation
Done
08 Oct 2026, 09:13 PM · Dada
FINAL RA Measurement Received
Done
27 Oct 2026, 01:42 PM · Dada

Complete visit timeline

14 visits
27 Oct 2026, 01:42 PM
Dada · PPR-2026-10-00353
Step updates
odu unit installation · DoneFINAL RA Measurement Received · Done
ActivityCable tray cover installation done.
Tomorrow's planNo
09 Oct 2026, 10:01 PM
Jay Bhosale · PPR-2026-10-00301
Activity1 st floor AC working normal conditions
Tomorrow's planAll ground floor AC panels installation & Commissiong
08 Oct 2026, 10:33 PM
Jay Bhosale · PPR-2026-10-00298
ActivityNitrogen on hold
Tomorrow's planPending work of panels installation & Commissiong
08 Oct 2026, 09:13 PM
Dada · PPR-2026-10-00296
Step updates
LS Material Delivery · DoneFan Installation · Done
ActivityGround floor Indoor unit installation work Done with Final Nitrogen presure testing done
Tomorrow's planPlanned for tomorrow: Pre-Commissioning.
07 Oct 2026, 10:27 PM
Jay Bhosale · PPR-2026-10-00294
Step updates
LS Material Delivery · Done
Activity11 Indoor AC Recieved & 8 Installation done
Tomorrow's planRemaining AC installation & nitrogen Holding
06 Oct 2026, 11:15 PM
Jay Bhosale · PPR-2026-10-00289
Step updates
LS Material Delivery · Done
ActivityGround floor AC Supporter installation done
Tomorrow's planIndoor AC installation
05 Oct 2026, 11:32 PM
Jay Bhosale · PPR-2026-10-00279
ActivityAC Supporter installation done
Tomorrow's planIndoor AC installation
29 Sep 2026, 05:52 PM
Jay Bhosale · PPR-2026-09-00253
Step updates
Grill Installation · Done
ActivityWiring in Kalashetram & Grills installation & 350 PSI System pressure testing done, Covering 7 AC done
Tomorrow's planRemote
Indoor
15 Sep 2026, 08:07 PM
Dada · PPR-2026-09-00225
ActivityIndoor unit proper cover with plastic.
Tomorrow's planGround floor balance work started
09 Sep 2026, 03:01 PM
Dada · PPR-2026-09-00208
Step updates
IDU/ODU Pressure Testing · Doneodu unit installation · DoneFinal Nitrogen Testing · Done
ActivityFinal Nitrogen Testing completed today.at 1 t
Tomorrow's planNo plan
04 Sep 2026, 09:36 PM
Dada · PPR-2026-09-00197
Step updates
HS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Done
ActivityIndoor unit installation work
Tomorrow's planNo
31 Aug 2026, 09:26 PM
Dada · PPR-2026-08-00177
Step updates
Marking · Doneodu unit installation · Done
Activity1 st floor indoor unit marking Done. & Show to Yogesh Sir YK Kaka & Sagar sir then start for Cutting.
Odu Unit shifting at Location with stand
Tomorrow's planOut side tray installation work
28 Aug 2026, 05:59 PM
Dada · PPR-2026-08-00169
ActivityOdu Unit shifting work done
Tomorrow's planRemote
19 Aug 2026, 01:11 PM
Dada · PPR-2026-08-00135
Step updates
Civil Opening · DoneSupport · DoneCopper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneFresh Air - PVC PIPE / Duct · Done
ActivityVisit site
Tomorrow's planNo plan

Photos and files

5 attachments

Report processing

partial
photo save
done
27 Oct 2026, 01:43 PM
4 photo(s) uploaded
sheet write
done
27 Oct 2026, 01:43 PM
1 row(s) written
pms update
done
27 Oct 2026, 01:43 PM
PMS row stamped — 7 cell(s)
pdf
done
27 Oct 2026, 01:43 PM
PDF built
email
done
27 Oct 2026, 01:47 PM
emailed
whatsapp
failed
27 Oct 2026, 01:47 PM
no client number