PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)

PPR-2026-09-00222 · 12 Sep 2026, 10:53 PM
EngineerPratik
Site typeNon-VRV · General
People on site2
ActivityCasing patti for IDU installation completed today. Drain connection completed.
Tomorrow's planSunday
Next step date

Current project steps

23 tracked
HS Material Delivery IDU
Done
29 Aug 2026, 10:18 PM · Pratik
HS Material Delivery ODU
Done
29 Aug 2026, 10:18 PM · Pratik
LS Material Delivery
Done
29 Aug 2026, 10:18 PM · Pratik
Main Ducting Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Main Ducting
Not required
02 Sep 2026, 11:41 PM · Pratik
Drain Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Copper Piping Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Underdake Insulation
Not required
02 Sep 2026, 11:41 PM · Pratik
Collar
Not required
02 Sep 2026, 11:41 PM · Pratik
IDU Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
ODU Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Fan Installation
Not required
02 Sep 2026, 11:41 PM · Pratik
Disk Valve
Not required
02 Sep 2026, 11:41 PM · Pratik
Support
Done
02 Sep 2026, 11:41 PM · Pratik
Copper Piping
Done
03 Sep 2026, 11:53 PM · Pratik
Indoor Installation
Done
07 Sep 2026, 11:51 PM · Pratik
odu unit installation
Done
07 Sep 2026, 11:51 PM · Pratik
Cable
Done
11 Sep 2026, 11:42 PM · Pratik
Drain
Done
11 Sep 2026, 11:42 PM · Pratik
LS Pressure Testing
Done
11 Sep 2026, 11:42 PM · Pratik
IDU/ODU Pressure Testing
Done
11 Sep 2026, 11:42 PM · Pratik
Final Nitrogen Testing
Done
11 Sep 2026, 11:42 PM · Pratik
Commissining
Done
11 Sep 2026, 11:42 PM · Pratik

Complete visit timeline

7 visits
12 Sep 2026, 10:53 PM
Pratik · PPR-2026-09-00222
ActivityCasing patti for IDU installation completed today. Drain connection completed.
Tomorrow's planSunday
11 Sep 2026, 11:42 PM
Pratik · PPR-2026-09-00217
Step updates
Cable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · DoneFinal Nitrogen Testing · DoneCommissining · Done
ActivityCommissining completed today.
Tomorrow's plan-
07 Sep 2026, 11:51 PM
Pratik · PPR-2026-09-00203
Step updates
Indoor Installation · Doneodu unit installation · Done
ActivityIndoor Installation completed today. odu unit installation completed today.
Tomorrow's plan-
04 Sep 2026, 11:28 PM
Pratik · PPR-2026-09-00201
ActivitySupporting for IDU installation
Tomorrow's planPlanned for tomorrow: Indoor Installation. · starts 05 Sep 2026
03 Sep 2026, 11:53 PM
Pratik · PPR-2026-09-00192
Step updates
Copper Piping · Done
ActivityCopper Piping completed today.
Tomorrow's planFabrication
02 Sep 2026, 11:41 PM
Pratik · PPR-2026-09-00189
Step updates
Main Ducting Dismental · Not requiredMain Ducting · Not requiredDrain Dismental · Not requiredCopper Piping Dismental · Not requiredUnderdake Insulation · Not requiredCollar · Not requiredIDU Dismental · Not requiredODU Dismental · Not requiredFan Installation · Not requiredDisk Valve · Not requiredSupport · Done
ActivitySupport completed today.
Tomorrow's planPlanned for tomorrow: Copper Piping.
29 Aug 2026, 10:18 PM
Pratik · PPR-2026-08-00172
Step updates
HS Material Delivery IDU · DoneHS Material Delivery ODU · DoneLS Material Delivery · Done
ActivityHS Material Delivery ODU completed today. HS Material Delivery IDU completed today. LS Material Delivery completed today.
Tomorrow's planSunday.

Photos and files

4 attachments

Report processing

done
photo save
done
12 Sep 2026, 10:55 PM
3 photo(s) uploaded
sheet write
done
12 Sep 2026, 10:55 PM
1 row(s) written
pms update
done
12 Sep 2026, 10:55 PM
PMS row stamped
pdf
done
12 Sep 2026, 10:55 PM
PDF built
email
skipped
12 Sep 2026, 10:59 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
12 Sep 2026, 10:59 PM
Other Activity visit — report kept in-house, not sent to the client.