Kalashetram Silk And Sarees(Ground Floor & First Floor)

PPR-2026-09-00225 · 15 Sep 2026, 08:07 PM
EngineerDada
Site typeVRV · General
People on site
ActivityIndoor unit proper cover with plastic.
Tomorrow's planGround floor balance work started
Next step date

Current project steps

14 tracked
Civil Opening
Done
19 Aug 2026, 01:11 PM · Dada
Support
Done
19 Aug 2026, 01:11 PM · Dada
Copper Piping
Done
19 Aug 2026, 01:11 PM · Dada
Cable
Done
19 Aug 2026, 01:11 PM · Dada
Drain
Done
19 Aug 2026, 01:11 PM · Dada
LS Pressure Testing
Done
19 Aug 2026, 01:11 PM · Dada
Fresh Air - PVC PIPE / Duct
Done
19 Aug 2026, 01:11 PM · Dada
Marking
Done
31 Aug 2026, 09:26 PM · Dada
odu unit installation
Done
09 Sep 2026, 03:01 PM · Dada
HS Material Delivery IDU
Done
04 Sep 2026, 09:36 PM · Dada
HS Material Delivery ODU
Done
04 Sep 2026, 09:36 PM · Dada
Indoor Installation
Done
04 Sep 2026, 09:36 PM · Dada
IDU/ODU Pressure Testing
Done
09 Sep 2026, 03:01 PM · Dada
Final Nitrogen Testing
Done
09 Sep 2026, 03:01 PM · Dada

Complete visit timeline

6 visits
15 Sep 2026, 08:07 PM
Dada · PPR-2026-09-00225
ActivityIndoor unit proper cover with plastic.
Tomorrow's planGround floor balance work started
09 Sep 2026, 03:01 PM
Dada · PPR-2026-09-00208
Step updates
IDU/ODU Pressure Testing · Doneodu unit installation · DoneFinal Nitrogen Testing · Done
ActivityFinal Nitrogen Testing completed today.at 1 t
Tomorrow's planNo plan
04 Sep 2026, 09:36 PM
Dada · PPR-2026-09-00197
Step updates
HS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Done
ActivityIndoor unit installation work
Tomorrow's planNo
31 Aug 2026, 09:26 PM
Dada · PPR-2026-08-00177
Step updates
Marking · Doneodu unit installation · Done
Activity1 st floor indoor unit marking Done. & Show to Yogesh Sir YK Kaka & Sagar sir then start for Cutting.
Odu Unit shifting at Location with stand
Tomorrow's planOut side tray installation work
28 Aug 2026, 05:59 PM
Dada · PPR-2026-08-00169
ActivityOdu Unit shifting work done
Tomorrow's planRemote
19 Aug 2026, 01:11 PM
Dada · PPR-2026-08-00135
Step updates
Civil Opening · DoneSupport · DoneCopper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneFresh Air - PVC PIPE / Duct · Done
ActivityVisit site
Tomorrow's planNo plan

Photos and files

8 attachments

Report processing

done
photo save
done
15 Sep 2026, 08:08 PM
7 photo(s) uploaded
sheet write
done
15 Sep 2026, 08:08 PM
1 row(s) written
pms update
done
15 Sep 2026, 08:08 PM
PMS row stamped
pdf
done
15 Sep 2026, 08:08 PM
PDF built
email
skipped
15 Sep 2026, 08:12 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
15 Sep 2026, 08:12 PM
Other Activity visit — report kept in-house, not sent to the client.