GAURAV ICON TOWER (8th floor)

PPR-2026-11-00415 · 17 Nov 2026, 09:54 PM
Open
EngineerNagraj
Site typeVRV · General
People on site2
ActivityAll indoor units installation done
Copper pipe connection done
Drain piping connection done
Tomorrow's planPlanned for tomorrow: odu unit installation, Cable, Fan Installation. Communication cabling connection
Pintop fixing and connection
Drain piping
Next step date18 Nov 2026

Current project steps

2 tracked
Cable
Open
17 Nov 2026, 09:54 PM · Nagraj
Drain
Open
17 Nov 2026, 09:54 PM · Nagraj

Complete visit timeline

1 visit
17 Nov 2026, 09:54 PM
Nagraj · PPR-2026-11-00415
Step updates
Cable · OpenDrain · Open
ActivityAll indoor units installation done
Copper pipe connection done
Drain piping connection done
Tomorrow's planPlanned for tomorrow: odu unit installation, Cable, Fan Installation. Communication cabling connection
Pintop fixing and connection
Drain piping · starts 18 Nov 2026

Photos and files

0 attachments
No uploaded files are available for this report.