Kasturi › Balmoral River side D-wing › Basement ventatilation

PPR-2026-11-00377 · 02 Nov 2026, 08:43 PM
Open
EngineerShubham
Site typeVentilation · Developer
People on site2
ActivityCable tray hanging, marking work on going
Tomorrow's planMarking work on going
Next step date—

Current project steps

4 tracked
Jet Marking
Done
23 Oct 2026, 09:43 PM · Shubham
Jet Supporting
Done
23 Oct 2026, 09:43 PM · Shubham
Jet Installation
Done
23 Oct 2026, 09:43 PM · Shubham
Cable Supporting
Open
02 Nov 2026, 08:43 PM · Shubham

Complete visit timeline

2 visits
02 Nov 2026, 08:43 PM
Shubham · PPR-2026-11-00377
Step updates
Cable Supporting · Open
ActivityCable tray hanging, marking work on going
Tomorrow's planMarking work on going
23 Oct 2026, 09:43 PM
Shubham · PPR-2026-10-00340
Step updates
Jet Marking · DoneJet Supporting · DoneJet Installation · Done
ActivityCable tray hanging, marking work on going
Tomorrow's planDrilling, marking, supporting work on going

Photos and files

3 attachments

Report processing

partial
photo save
done
02 Nov 2026, 08:44 PM
2 photo(s) uploaded
sheet write
done
02 Nov 2026, 08:44 PM
1 row(s) written
pms update
done
02 Nov 2026, 08:44 PM
PMS row stamped — 2 cell(s) · NOT WRITTEN: Tentative end date
pdf
done
02 Nov 2026, 08:44 PM
PDF built
email
done
02 Nov 2026, 08:48 PM
emailed
whatsapp
failed
02 Nov 2026, 08:48 PM
no client number