Deepak Fertilisers And Petrochemicals Corporation Limited

PPR-2026-10-00350 · 26 Oct 2026, 09:39 PM
—
EngineerJay Bhosale
Site typePAC/CRAC · General
People on site2
ActivityPipe connection done
Form Client Electrical Panel Power Supply wire connection done
Tomorrow's plan4 AC Vaccum pending
Outdoor Power Supply wire connection
Next step date—

Current project steps

1 tracked
LS Material Delivery
Done
16 Oct 2026, 09:55 PM · Jay Bhosale

Complete visit timeline

21 visits
14 Nov 2026, 10:49 PM
Jay Bhosale · PPR-2026-11-00400
Activity*Today Site Report*

14/11/2026(Saturday)

Site Name = Deepak Fertilizer (Taloja)



*Work Done*


P-1) 16 Nos Tower AC Testing done

P-2) Tower AC Indoor pipe & cable goes this side close with PU
Tomorrow's planFinal AC Testing
13 Nov 2026, 09:58 PM
Jay Bhosale · PPR-2026-11-00397
ActivityAll Tower AC Testing
Tomorrow's planReturn Tower AC Testing
06 Nov 2026, 10:05 PM
Jay Bhosale · PPR-2026-11-00395
ActivityTower AC Testing
Tomorrow's planFinal Testing
05 Nov 2026, 10:12 PM
Jay Bhosale · PPR-2026-11-00393
ActivityTower AC Testing done & Remaining Gas charging done
Tomorrow's planTower AC Final Testing
04 Nov 2026, 11:18 PM
Jay Bhosale · PPR-2026-11-00390
ActivityPanel checking in work done
Tomorrow's planTower AC Testing
03 Nov 2026, 07:05 PM
Jay Bhosale · PPR-2026-11-00386
ActivityTower AC Indoor To Outdoor Earthing cable connection Work done
Tomorrow's planTower AC checking
03 Nov 2026, 09:54 AM
Jay Bhosale · PPR-2026-11-00381
ActivityPanel Wiring & Tower AC connection check
Tomorrow's planPanel check
31 Oct 2026, 11:55 PM
Jay Bhosale · PPR-2026-10-00374
Activity2 tower AC testing
Tomorrow's planMonday plan electrical panels Checking
30 Oct 2026, 10:20 PM
Jay Bhosale · PPR-2026-10-00369
ActivityAll Tower AC Outdoor Wire connection done & also Earthing cable connection
Tomorrow's planAll Tower AC Testing
29 Oct 2026, 11:04 PM
Jay Bhosale · PPR-2026-10-00363
Activity6 Nos Tower AC Testing done
Temperature Display 2 Nos
Tomorrow's planAll Tower AC On Testing
28 Oct 2026, 09:07 PM
Jay Bhosale · PPR-2026-10-00357
Activity4 Tower AC vaccum done
8 Nos Tower AC wire connection done (Panel Room) Side
Tomorrow's planPending Tower AC Wire connection to Panel
27 Oct 2026, 10:38 PM
Jay Bhosale · PPR-2026-10-00356
ActivityIndoor AC Pipe connection
Tomorrow's planTower AC outdoor wire connection & AC Vaccum
26 Oct 2026, 09:39 PM
Jay Bhosale · PPR-2026-10-00350
ActivityPipe connection done
Form Client Electrical Panel Power Supply wire connection done
Tomorrow's plan4 AC Vaccum pending
Outdoor Power Supply wire connection
25 Oct 2026, 07:18 PM
Jay Bhosale · PPR-2026-10-00346
ActivityPanel Room (Server) outdoor pipe connection done
Tomorrow's planTower AC vaccum & pending work
24 Oct 2026, 11:37 PM
Jay Bhosale · PPR-2026-10-00344
ActivityAll Tower AC Indoor & Outdoor installation done & ANP & WNA Lab pipe connection done
Tomorrow's planPanel Room (Server) Pipe connection work
23 Oct 2026, 09:10 PM
Jay Bhosale · PPR-2026-10-00339
Activity14 Outdoor installation done
Tomorrow's plan17 Tower AC pipe connection & testing
22 Oct 2026, 08:33 PM
Jay Bhosale · PPR-2026-10-00337
ActivityTower AC placed their requirement location with cooling area & outdoor installation done 2
Tomorrow's planAll Tower connection & Trial with Testing
21 Oct 2026, 10:02 PM
Jay Bhosale · PPR-2026-10-00332
ActivityANP & WNA Lab Indoor Tower AC Placed this as per design
Tomorrow's planTower AC installation & Testing
16 Oct 2026, 09:55 PM
Jay Bhosale · PPR-2026-10-00325
Step updates
LS Material Delivery · Done
ActivityTower AC Recieved & with Installation Meterials
Tomorrow's planTower AC installation with Testing
01 Oct 2026, 08:35 PM
Jay Bhosale · PPR-2026-10-00263
ActivityMeeting Done

*Today Site Report*

1/10/2026(Thursday)

*Work done*



All this Materials kept in Container &
Container Locked


P-1) Cable & industrial Distribution Board,Panel connection


P-2)PPE Kit List

1) Safety shoes= 4 Nos
2) Helmet= 16 Nos
3) Jacket= 16 Nos
4) Safety Goggles= 6 Nos
5) Belt= 4 Nos


*Pending work Plan*


1) Tower AC = 17 Nos Upcoming at 8 October
Tomorrow's planTower AC Arrived 8 October
28 Sep 2026, 04:39 PM
Jay Bhosale · PPR-2026-09-00249
Step updates
LS Material Delivery · Done
Activity*Today Site Report*

28/9/2026(Monday)

*Work done*

1) Electrical Panel & Cable Arrived & kept in Client direction Location

2)PPE Kit List kept in Ravindra Sir Office

1) Safety shoes= 4 Nos
2) Helmet= 16 Nos
3) Jacket= 16 Nos
4) Safety Goggles= 6 Nos
5) Belt= 4 Nos


*Pending work Plan*

1) Electrical Panel Main Supply & Cable Connection

2) Container

3) Tower AC
Tomorrow's planPlanned for tomorrow: Marking.

Photos and files

5 attachments

Report processing

done
photo save
done
26 Oct 2026, 09:40 PM
4 photo(s) uploaded
sheet write
done
26 Oct 2026, 09:40 PM
1 row(s) written
pms update
done
26 Oct 2026, 09:40 PM
PMS row stamped — 3 cell(s)
pdf
done
26 Oct 2026, 09:40 PM
PDF built
email
skipped
26 Oct 2026, 09:44 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
26 Oct 2026, 09:44 PM
Other Activity visit — report kept in-house, not sent to the client.