KRA Jewellers(Krishna Rajaram Ashtekar)

PPR-2026-10-00358 · 28 Oct 2026, 09:10 PM
—
EngineerNagraj
Site typeVRV · General
People on site2
ActivityCRC addressing and demo given to branch manager

All exhaust fans working checked
Tomorrow's planNothing
Next step date—

Current project steps

5 tracked
Copper Piping
Open
06 Oct 2026, 09:06 PM · Nagraj
Drain
Open
06 Oct 2026, 09:06 PM · Nagraj
Fan Installation
Done
26 Oct 2026, 09:36 PM · Nagraj
Disk Valve
Done
27 Oct 2026, 10:26 PM · Nagraj
Commissioning
Done
27 Oct 2026, 10:26 PM · Nagraj

Complete visit timeline

4 visits
28 Oct 2026, 09:10 PM
Nagraj · PPR-2026-10-00358
ActivityCRC addressing and demo given to branch manager

All exhaust fans working checked
Tomorrow's planNothing
27 Oct 2026, 10:26 PM
Nagraj · PPR-2026-10-00355
Step updates
Disk Valve · DoneCommissioning · Done
ActivityDisc valve installation done

VRV system Commissioning done
Tomorrow's planCRC Addressing
26 Oct 2026, 09:36 PM
Nagraj · PPR-2026-10-00349
Step updates
Fan Installation · Done
ActivityBoth exhaust fans installation done...
Tomorrow's planPlanned for tomorrow: Commissioning, Disk Valve. CRC addressing · starts 27 Oct 2026
06 Oct 2026, 09:06 PM
Nagraj · PPR-2026-10-00287
Step updates
Copper Piping · OpenDrain · Open
ActivityGround floor split ac copper piping and drain piping
Tomorrow's planPlanned for tomorrow: Copper Piping, Cable, Drain. Outdoor unit copper piping in basement
CRC cabling · starts 07 Oct 2026

Photos and files

2 attachments

Report processing

done
photo save
done
28 Oct 2026, 09:11 PM
1 photo(s) uploaded
sheet write
done
28 Oct 2026, 09:11 PM
1 row(s) written
pms update
done
28 Oct 2026, 09:11 PM
PMS row stamped — 3 cell(s)
pdf
done
28 Oct 2026, 09:11 PM
PDF built
email
skipped
28 Oct 2026, 09:15 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
28 Oct 2026, 09:15 PM
Other Activity visit — report kept in-house, not sent to the client.