Avian Valley, Bhugaon

PPR-2026-08-00175 · 29 Aug 2026, 10:35 PM
Done
EngineerPratik
Site typeVRV · General
People on site
ActivityColoured panel received at site.
Tomorrow's planSunday
Next step date

Current project steps

30 tracked
LS Material Delivery
Done
29 Aug 2026, 10:35 PM · Pratik
Marking
Done
29 Aug 2026, 10:35 PM · Pratik
Support
Done
29 Aug 2026, 10:35 PM · Pratik
Copper Piping
Done
29 Aug 2026, 10:35 PM · Pratik
Cable
Done
29 Aug 2026, 10:35 PM · Pratik
Drain
Done
29 Aug 2026, 10:35 PM · Pratik
LS Pressure Testing
Done
29 Aug 2026, 10:35 PM · Pratik
IDU/ODU Pressure Testing
Done
29 Aug 2026, 10:35 PM · Pratik
Main Ducting
Done
29 Aug 2026, 10:35 PM · Pratik
Collar
Done
29 Aug 2026, 10:35 PM · Pratik
1st RA Measurement Submitted by PE
Done
29 Aug 2026, 10:35 PM · Pratik
HS Material Delivery IDU
Done
29 Aug 2026, 10:35 PM · Pratik
HS Material Delivery ODU
Done
29 Aug 2026, 10:35 PM · Pratik
Indoor Installation
Done
29 Aug 2026, 10:35 PM · Pratik
odu unit installation
Done
29 Aug 2026, 10:35 PM · Pratik
Final Nitrogen Testing
Done
29 Aug 2026, 10:35 PM · Pratik
Grill Installation
Done
29 Aug 2026, 10:35 PM · Pratik
Disk Valve
Done
29 Aug 2026, 10:35 PM · Pratik
Fan Installation
Done
29 Aug 2026, 10:35 PM · Pratik
FINAL RA Measurement Received
Done
29 Aug 2026, 10:35 PM · Pratik
Commissining
Done
29 Aug 2026, 10:35 PM · Pratik
ODU Dismental
Not required
29 Aug 2026, 10:35 PM · Pratik
IDU Dismental
Not required
29 Aug 2026, 10:35 PM · Pratik
Fresh Air - PVC PIPE / Duct
Not required
29 Aug 2026, 10:35 PM · Pratik
Main Ducting Dismental
Not required
29 Aug 2026, 10:35 PM · Pratik
Drain Dismental
Not required
29 Aug 2026, 10:35 PM · Pratik
Copper Piping Dismental
Not required
29 Aug 2026, 10:35 PM · Pratik
Civil Opening
Not required
29 Aug 2026, 10:35 PM · Pratik
Underdake Insulation
Not required
29 Aug 2026, 10:35 PM · Pratik
Pre-Commissining
Done
29 Aug 2026, 10:35 PM · Pratik

Complete visit timeline

3 visits
31 Aug 2026, 11:09 PM
Pratik · PPR-2026-08-00178
ActivityColoured panel installation done.
Tomorrow's plan-
29 Aug 2026, 10:35 PM
Pratik · PPR-2026-08-00175
Step updates
LS Material Delivery · DoneMarking · DoneSupport · DoneCopper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · DoneMain Ducting · DoneCollar · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Doneodu unit installation · DoneFinal Nitrogen Testing · DoneGrill Installation · DoneDisk Valve · DoneFan Installation · DoneFINAL RA Measurement Received · DoneCommissining · DoneODU Dismental · Not requiredIDU Dismental · Not requiredFresh Air - PVC PIPE / Duct · Not requiredMain Ducting Dismental · Not requiredDrain Dismental · Not requiredCopper Piping Dismental · Not requiredCivil Opening · Not requiredUnderdake Insulation · Not requiredPre-Commissining · Done
ActivityColoured panel received at site.
Tomorrow's planSunday
17 Aug 2026, 11:31 PM
Pratik · PPR-2026-08-00126
ActivitySample painting for panels.
Tomorrow's planPanel painting.

Photos and files

4 attachments

Report processing

done
photo save
done
29 Aug 2026, 10:36 PM
2 photo(s) uploaded
precommissioning report
done
29 Aug 2026, 10:36 PM
1 pre-commissioning report(s) attached
sheet write
done
29 Aug 2026, 10:36 PM
1 row(s) written
pms update
done
29 Aug 2026, 10:37 PM
PMS row stamped
pdf
done
29 Aug 2026, 10:37 PM
PDF built
email
done
29 Aug 2026, 10:41 PM
emailed
whatsapp
done
29 Aug 2026, 10:41 PM
SENT — doc media=1780362249768137