3rd Floor Mantry Building

PPR-2026-11-00396 · 13 Nov 2026, 04:39 PM
Open
EngineerAkash S
Site typeVRV · General
People on site—
ActivityCopper piping wip
Tomorrow's planWaiting for material delivery
Next step date—

Current project steps

12 tracked
LS Material Delivery
Open
15 Nov 2026, 01:14 PM · Akash S
HS Material Delivery ODU
Done
02 Nov 2026, 05:05 PM · Kishor Nannaware
Marking
Done
06 Nov 2026, 05:22 PM · Kishor Nannaware
Support
Done
06 Nov 2026, 05:22 PM · Kishor Nannaware
Copper Piping
Open
16 Nov 2026, 06:48 PM · Akash S
Drain
Open
13 Nov 2026, 04:39 PM · Akash S
Cable
Open
13 Nov 2026, 04:39 PM · Akash S
Underdake Insulation
Not required
17 Nov 2026, 06:42 PM · Akash S
Drain Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
Main Ducting Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
IDU Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
ODU Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S

Complete visit timeline

8 visits
17 Nov 2026, 06:42 PM
Akash S · PPR-2026-11-00411
Step updates
Underdake Insulation · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not required
ActivityCommunication Cable wip ,
8 cassette ac recieved, 14 panels received
Tomorrow's planPlanned for tomorrow: Cable, odu unit installation.
16 Nov 2026, 06:48 PM
Akash S · PPR-2026-11-00406
Step updates
Copper Piping · Open
ActivityWindow dismantled for odu shifting .
Tomorrow's planPlanned for tomorrow: Copper Piping. Copper piping wip
15 Nov 2026, 01:14 PM
Akash S · PPR-2026-11-00401
Step updates
LS Material Delivery · Open
ActivityConversation done about window opening and shifting of odu .
Tomorrow's planPlanned for tomorrow: odu unit installation. Odu positioning
13 Nov 2026, 04:39 PM
Akash S · PPR-2026-11-00396
Step updates
Copper Piping · OpenDrain · OpenCable · Open
ActivityCopper piping wip
Tomorrow's planWaiting for material delivery
06 Nov 2026, 05:22 PM
Kishor Nannaware · PPR-2026-11-00394
Step updates
Marking · DoneSupport · Done
ActivityHalf area supporting completed.
Tomorrow's planSupporting of copper pipe
02 Nov 2026, 05:05 PM
Kishor Nannaware · PPR-2026-11-00376
Step updates
HS Material Delivery ODU · Done
Activity2 nos of ODU received at site
Tomorrow's planPlanned for tomorrow: Marking, Support.
31 Oct 2026, 06:54 PM
Kishor Nannaware · PPR-2026-10-00371
Step updates
LS Material Delivery · Done
ActivityLow side material delivered at site.
Tomorrow's planNo work Tommorow
29 Oct 2026, 04:57 PM
Dada · PPR-2026-10-00360
ActivityVendor visit and site clearance checking
Tomorrow's planPlanned for tomorrow: Civil Opening.

Photos and files

8 attachments

Report processing

done
photo save
done
13 Nov 2026, 04:40 PM
7 photo(s) uploaded
sheet write
done
13 Nov 2026, 04:40 PM
1 row(s) written
pms update
done
13 Nov 2026, 04:40 PM
PMS row stamped — 6 cell(s)
pdf
done
13 Nov 2026, 04:40 PM
PDF built
email
done
13 Nov 2026, 04:46 PM
emailed
whatsapp
done
13 Nov 2026, 04:46 PM
SENT — doc media=982854344420952