GAURAV ICON TOWER (7th floor)

PPR-2026-10-00324 · 16 Oct 2026, 09:51 PM
Open
EngineerNagraj
Site typeVRV · General
People on site2
Activity5nos indoor units installation done
Copper piping and drain piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation. No
Next step date17 Oct 2026

Current project steps

6 tracked
Marking
Open
09 Oct 2026, 11:07 PM · Nagraj
Fresh Air - PVC PIPE / Duct
Open
09 Oct 2026, 11:07 PM · Nagraj
Indoor Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Fan Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Disk Valve
Open
24 Oct 2026, 10:39 PM · Nagraj
Final Nitrogen Testing
Open
24 Oct 2026, 10:39 PM · Nagraj

Complete visit timeline

6 visits
24 Oct 2026, 10:39 PM
Nagraj · PPR-2026-10-00343
Step updates
Disk Valve · OpenFinal Nitrogen Testing · Open
ActivityFinal Nitrogen pressure testing in progress
Tomorrow's planPlanned for tomorrow: Pre-Commissioning.
17 Oct 2026, 11:25 PM
Nagraj · PPR-2026-10-00328
Step updates
Indoor Installation · OpenFan Installation · Open
ActivityReception area machine installation done.

6nos machines copper piping and drain piping work completed

Split ac installation done.

1no fresh air fan installation done
Tomorrow's planPlanned for tomorrow: odu unit installation.
16 Oct 2026, 09:51 PM
Nagraj · PPR-2026-10-00324
Step updates
Indoor Installation · Open
Activity5nos indoor units installation done
Copper piping and drain piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation. No · starts 17 Oct 2026
14 Oct 2026, 11:18 PM
Pratik · PPR-2026-10-00318
Activity2 Nos - Split IDU and ODU received at site today.
Tomorrow's plan-
10 Oct 2026, 06:55 PM
Nagraj · PPR-2026-10-00305
Step updates
Indoor Installation · Open
ActivityIndoor units installation started
Tomorrow's planPlanned for tomorrow: Indoor Installation, Copper Piping, Drain. Indoor units installation
Copper pipe connection
Drain pipe connection · starts 12 Oct 2026
09 Oct 2026, 11:07 PM
Nagraj · PPR-2026-10-00303
Step updates
Marking · OpenFresh Air - PVC PIPE / Duct · Open
ActivityAll idu marking done

6nos machines rod fixing done

Fresh PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, Fresh Air - PVC PIPE / Duct, Drain. · starts 10 Oct 2026

Photos and files

7 attachments

Report processing

done
photo save
done
16 Oct 2026, 09:52 PM
6 photo(s) uploaded
sheet write
done
16 Oct 2026, 09:52 PM
1 row(s) written
pms update
done
16 Oct 2026, 09:52 PM
PMS row stamped — 5 cell(s)
pdf
done
16 Oct 2026, 09:52 PM
PDF built
email
done
16 Oct 2026, 09:59 PM
emailed
whatsapp
done
16 Oct 2026, 09:59 PM
SENT — doc media=1638218284522065