Ultra Unit - 6 Production Office ( First Floor)

PPR-2026-10-00322 · 15 Oct 2026, 11:55 PM
—
EngineerPratik
Site typeVRV · General
People on site—
Activity6 Nos IDU received at site today.
Tomorrow's plan-
Next step date—

Current project steps

21 tracked
Marking
Done
13 Aug 2026, 06:59 PM · Pratik
Support
Done
20 Aug 2026, 09:42 PM · Pratik
IDU Dismental
Not required
03 Sep 2026, 11:55 PM · Pratik
Copper Piping Dismental
Not required
03 Sep 2026, 11:55 PM · Pratik
Drain Dismental
Not required
03 Sep 2026, 11:55 PM · Pratik
Underdake Insulation
Not required
03 Sep 2026, 11:55 PM · Pratik
Civil Opening
Not required
03 Sep 2026, 11:55 PM · Pratik
Main Ducting Dismental
Not required
03 Sep 2026, 11:55 PM · Pratik
Copper Piping
Done
03 Sep 2026, 11:55 PM · Pratik
Cable
Done
03 Sep 2026, 11:55 PM · Pratik
Drain
Done
03 Sep 2026, 11:55 PM · Pratik
LS Pressure Testing
Done
03 Sep 2026, 11:55 PM · Pratik
ODU Dismental
Not required
03 Sep 2026, 11:55 PM · Pratik
Main Ducting
Done
04 Sep 2026, 11:24 PM · Pratik
HS Material Delivery ODU
Done
08 Sep 2026, 11:47 PM · Pratik
HS Material Delivery IDU
Done
30 Sep 2026, 10:41 PM · Pratik
1st RA Measurement Submitted by PE
Done
10 Oct 2026, 11:32 PM · Pratik
Indoor Installation
Done
13 Oct 2026, 10:29 PM · Pratik
odu unit installation
Done
02 Nov 2026, 11:45 PM · Pratik
Fresh Air - PVC PIPE / Duct
Done
15 Nov 2026, 07:45 PM · Pratik
Grill Installation
Done
17 Nov 2026, 12:48 AM · Pratik

Complete visit timeline

17 visits
17 Nov 2026, 12:48 AM
Pratik · PPR-2026-11-00408
Step updates
Grill Installation · Done
ActivityPanels installation done.
Tomorrow's plan-
15 Nov 2026, 07:45 PM
Pratik · PPR-2026-11-00403
Step updates
Fresh Air - PVC PIPE / Duct · Done
ActivityFresh Air - PVC PIPE / Duct completed yesterday.
Tomorrow's planRemaining fresh air work.
02 Nov 2026, 11:45 PM
Pratik · PPR-2026-11-00379
Step updates
odu unit installation · Done
Activityodu unit installation completed today.
Tomorrow's plan-
29 Oct 2026, 11:31 PM
Pratik · PPR-2026-10-00364
ActivityODU shifting done.
Drain connection completed.
Tomorrow's planCable connection
22 Oct 2026, 07:01 PM
Pratik · PPR-2026-10-00335
ActivityRemaining IDU installation completed today.
Tomorrow's planMaterial delivery.
15 Oct 2026, 11:55 PM
Pratik · PPR-2026-10-00322
Activity6 Nos IDU received at site today.
Tomorrow's plan-
13 Oct 2026, 10:29 PM
Pratik · PPR-2026-10-00314
Step updates
Indoor Installation · Done
ActivityIndoor Installation completed today.
Tomorrow's plan-
10 Oct 2026, 11:32 PM
Pratik · PPR-2026-10-00307
Step updates
1st RA Measurement Submitted by PE · Done
ActivityIDU's received at site.
Tomorrow's planSunday
30 Sep 2026, 10:41 PM
Pratik · PPR-2026-09-00261
Step updates
HS Material Delivery IDU · Done
ActivityHS Material Delivery Panels completed today.
Tomorrow's plan-
23 Sep 2026, 11:57 PM
Pratik · PPR-2026-09-00244
ActivityMeasurements report created today.
Tomorrow's plan-
08 Sep 2026, 11:47 PM
Pratik · PPR-2026-09-00207
Step updates
HS Material Delivery ODU · Done
ActivityHS Material Delivery ODU completed today.
Tomorrow's plan-
04 Sep 2026, 11:24 PM
Pratik · PPR-2026-09-00198
Step updates
Main Ducting · Done
ActivityMain Ducting completed today.
Tomorrow's plan-
03 Sep 2026, 11:55 PM
Pratik · PPR-2026-09-00193
Step updates
Underdake Insulation · Not requiredCivil Opening · Not requiredCopper Piping Dismental · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredCopper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneIDU Dismental · Not requiredODU Dismental · Not required
ActivityLS Pressure Testing completed today.
Tomorrow's plan-
27 Aug 2026, 11:08 PM
Pratik · PPR-2026-08-00168
Step updates
Copper Piping Dismental · Not requiredDrain Dismental · Not required
ActivityRemaining copper piping.
Tomorrow's planDrain piping.
21 Aug 2026, 11:01 PM
Pratik · PPR-2026-08-00149
Step updates
IDU Dismental · Not required
ActivityRemaining supporting for copper piping.
Tomorrow's planCopper piping.
20 Aug 2026, 09:42 PM
Pratik · PPR-2026-08-00142
Step updates
Support · Done
ActivitySupport completed today.
Tomorrow's planPlanned for tomorrow: Copper Piping.
13 Aug 2026, 06:59 PM
Pratik · PPR-2026-08-00108
Step updates
Marking · Done
ActivityMarking completed today. Supporting done for 4 IDU'S. Tomorrow and day after tomorrow no team will be at site. On sunday team will be on site for work.
Tomorrow's planTomorrow and day after tomorrow no team will be at site. On sunday team will be on site for work.

Photos and files

2 attachments

Report processing

done
photo save
done
15 Oct 2026, 11:57 PM
1 photo(s) uploaded
sheet write
done
15 Oct 2026, 11:57 PM
1 row(s) written
pms update
done
15 Oct 2026, 11:57 PM
PMS row stamped — 3 cell(s)
pdf
done
15 Oct 2026, 11:57 PM
PDF built
email
skipped
16 Oct 2026, 12:01 AM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
16 Oct 2026, 12:01 AM
Other Activity visit — report kept in-house, not sent to the client.