Pankaj Runwal Residence

PPR-2026-09-00190 · 03 Sep 2026, 08:47 PM
Done
EngineerDada
Site typeVRV · General
People on site1
ActivityFinal Nitrogen presure testing work.
Tomorrow's planNo plan
Next step date

Current project steps

11 tracked
LS Material Delivery
Done
06 Aug 2026, 04:16 PM · Dada
IDU/ODU Pressure Testing
Open
06 Aug 2026, 04:16 PM · Dada
Final Nitrogen Testing
Done
03 Sep 2026, 08:47 PM · Dada
Grill Installation
Open
06 Aug 2026, 04:16 PM · Dada
Disk Valve
Open
06 Aug 2026, 04:16 PM · Dada
FINAL RA Measurement Received
Open
06 Aug 2026, 04:16 PM · Dada
Pre-Commissining
Open
06 Aug 2026, 04:16 PM · Dada
Commissining
Open
06 Aug 2026, 04:16 PM · Dada
HS Material Delivery ODU
Done
25 Aug 2026, 03:26 PM · Dada
HS Material Delivery IDU
Done
25 Aug 2026, 03:26 PM · Dada
odu unit installation
Done
02 Sep 2026, 10:54 AM · Dada

Complete visit timeline

7 visits
03 Sep 2026, 08:47 PM
Dada · PPR-2026-09-00190
Step updates
Final Nitrogen Testing · Done
ActivityFinal Nitrogen presure testing work.
Tomorrow's planNo plan
02 Sep 2026, 10:54 AM
Dada · PPR-2026-09-00183
Step updates
odu unit installation · Done
ActivityIndoor unit installation marking Done.
Tomorrow's planMeeting attend at site with Anil sir
27 Aug 2026, 03:02 PM
Dada · PPR-2026-08-00163
Step updates
odu unit installation · Done
ActivityOdu Unit installation work
Tomorrow's planNo Plan
26 Aug 2026, 05:30 PM
Dada · PPR-2026-08-00159
ActivityDucting collar installation done 1 st floor
Tomorrow's planOdu Unit shifting & Copper pipe conection work
25 Aug 2026, 03:26 PM
Dada · PPR-2026-08-00156
Step updates
HS Material Delivery ODU · DoneHS Material Delivery IDU · Done
ActivityWalk in wardrobe area Supply Duct collar Fabrication work
Tomorrow's planOdu Unit shifting & Ducting Collar installation.
13 Aug 2026, 07:12 PM
Dada · PPR-2026-08-00109
ActivitySite visit with Daikin Engg Mr Sachin Gunjal sir
Tomorrow's planNo plan
06 Aug 2026, 04:16 PM
Dada · PPR-2026-08-00066
Step updates
LS Material Delivery · DoneIDU/ODU Pressure Testing · OpenFinal Nitrogen Testing · OpenGrill Installation · OpenDisk Valve · OpenFINAL RA Measurement Received · OpenPre-Commissining · OpenCommissining · OpenHS Material Delivery ODU · Done
ActivityMeeting at Site With Anil Ranka Sir .
Tomorrow's planNo plan

Photos and files

1 attachment
SitePhoto_1_scaled_130904.jpg

Report processing

failed
photo save
done
03 Sep 2026, 08:48 PM
1 photo(s) uploaded
sheet write
failed
03 Sep 2026, 08:48 PM
Google API GET failed (HTTP 503): The service is currently unavailable.