Mushroom Cold Storage at Khadkwasla

PPR-2026-10-00327 · 17 Oct 2026, 05:29 PM
Done
EngineerDnyaneshwar G
Site typeVRV · General
People on site2
Activity10 Split AC copper piping, Communication cable and Drain piping work completed.
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation.
Next step date19 Oct 2026

Current project steps

17 tracked
LS Material Delivery
Done
05 Oct 2026, 06:30 PM · Reena
Marking
Done
05 Oct 2026, 06:30 PM · Reena
Support
Done
05 Oct 2026, 06:30 PM · Reena
HS Material Delivery IDU
Done
05 Oct 2026, 06:30 PM · Reena
HS Material Delivery ODU
Done
05 Oct 2026, 06:30 PM · Reena
Underdake Insulation
Not required
05 Oct 2026, 06:30 PM · Reena
Copper Piping Dismental
Not required
05 Oct 2026, 06:30 PM · Reena
Drain Dismental
Not required
05 Oct 2026, 06:30 PM · Reena
Main Ducting Dismental
Not required
05 Oct 2026, 06:30 PM · Reena
IDU Dismental
Not required
05 Oct 2026, 06:30 PM · Reena
ODU Dismental
Not required
05 Oct 2026, 06:30 PM · Reena
IDU/ODU Pressure Testing
Open
16 Oct 2026, 06:31 PM · Dnyaneshwar G
Copper Piping
Done
17 Oct 2026, 05:29 PM · Dnyaneshwar G
Cable
Done
17 Oct 2026, 05:29 PM · Dnyaneshwar G
Drain
Done
17 Oct 2026, 05:29 PM · Dnyaneshwar G
Indoor Installation
Done
19 Oct 2026, 07:02 PM · Dnyaneshwar G
odu unit installation
Open
21 Oct 2026, 05:35 PM · Dnyaneshwar G

Complete visit timeline

6 visits
21 Oct 2026, 05:35 PM
Dnyaneshwar G · PPR-2026-10-00331
Step updates
odu unit installation · Open
Activity07 Nos Outdoor Unit installation Done
Tomorrow's planPlanned for tomorrow: IDU/ODU Pressure Testing, odu unit installation. 03 Outdoor Unit stand not installed · starts 23 Oct 2026
19 Oct 2026, 07:02 PM
Dnyaneshwar G · PPR-2026-10-00329
Step updates
Indoor Installation · Done
Activity10 Split AC Indoor Installation completed
Tomorrow's planPlanned for tomorrow: odu unit installation. · starts 21 Oct 2026
17 Oct 2026, 05:29 PM
Dnyaneshwar G · PPR-2026-10-00327
Step updates
Copper Piping · DoneCable · DoneDrain · Done
Activity10 Split AC copper piping, Communication cable and Drain piping work completed.
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation. · starts 19 Oct 2026
16 Oct 2026, 06:31 PM
Dnyaneshwar G · PPR-2026-10-00323
Step updates
IDU/ODU Pressure Testing · OpenCopper Piping · Open
Activity1. 3 Chiller Units Copper Piping Pressure Testing Done
2. Split AC Copper Piping, Cable & Drain Piping work is in Progress
Tomorrow's planPlanned for tomorrow: Copper Piping, Cable, Drain, Indoor Installation.
06 Oct 2026, 04:54 PM
Dada · PPR-2026-10-00284
ActivityIn today’s meeting with Sohan Sir, the following activities were carried out:
1. Indoor unit level adjustment.
2. Revised copper piping and drain piping route, including panel cutout marking.
3. Finalization of Split AC indoor & outdoor unit locations, along with copper and drain piping routes.
4. Finalization of fresh air fan location and ducting route.
Tomorrow's planPlanned for tomorrow: Copper Piping.
05 Oct 2026, 06:30 PM
Reena · PPR-2026-10-00276
Step updates
LS Material Delivery · DoneMarking · DoneSupport · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneUnderdake Insulation · Not requiredCopper Piping Dismental · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not required
ActivityIDU, ODU for Cold room placed
Tomorrow's planPlanned for tomorrow: Civil Opening, Copper Piping. · starts 06 Oct 2026

Photos and files

10 attachments

Report processing

partial
photo save
done
17 Oct 2026, 05:30 PM
9 photo(s) uploaded
sheet write
done
17 Oct 2026, 05:30 PM
1 row(s) written
pms update
done
17 Oct 2026, 05:30 PM
PMS row stamped — 11 cell(s)
pdf
done
17 Oct 2026, 05:30 PM
PDF built
email
failed
17 Oct 2026, 05:39 PM
SMTP expected 250, got: 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp Transcript: < 220 smtp.gmail.com ESMTP 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-STARTTLS 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250 SMTPUTF8 > STARTTLS < 220 2.0.0 Ready to start TLS > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-AUTH LOGIN PLAIN XOAUTH2 PLAIN-CLIENTTOKEN OAUTHBEARER XOAUTH 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250 SMTPUTF8 > AUTH LOGIN < 334 VXNlcm5hbWU6 > Y3JtQHZha2hhcmlhYWlydGVjaC5jb20= < 334 UGFzc3dvcmQ6 > amt5byBiemppIGNycmQgc2RodA== < 235 2.7.0 Accepted > MAIL FROM:<crm@vakhariaairtech.com> < 250 2.1.0 OK 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > RCPT TO:<sohan.kogekar@gmail.com> < 250 2.1.5 OK 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > RCPT TO:<crm@vakhariaairtech.com> < 250 2.1.5 OK 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > RCPT TO:<piyush@vakhariaairtech.com> < 250 2.1.5 OK 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > DATA < 354 Go ahead 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp > Date: Sat, 17 Oct 2026 17:34:10 +0530 From: CRM Vakharia Airtech <crm@vakhariaairtech.com> To: sohan.kogekar@gmail.com… < 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError 5a478bee46e88-3608219f838sm14967432eec.19 - gsmtp (to sohan.kogekar@gmail.com)
whatsapp
done
17 Oct 2026, 05:39 PM
SENT — doc media=2497835047377736