Ultra Unit - 6 Production Office (Ground Floor)

PPR-2026-10-00365 · 29 Oct 2026, 11:33 PM
—
EngineerPratik
Site typeVRV · General
People on site3
ActivityODU shifting done.
Server room non VRV units received at site.
Tomorrow's planNon VRV units installation.
Next step date—

Current project steps

24 tracked
Marking
Done
26 Oct 2026, 10:59 PM · Pratik
Support
Done
26 Oct 2026, 10:59 PM · Pratik
Copper Piping
Done
26 Oct 2026, 10:59 PM · Pratik
Cable
Done
26 Oct 2026, 10:59 PM · Pratik
Drain
Done
26 Oct 2026, 10:59 PM · Pratik
LS Pressure Testing
Done
26 Oct 2026, 10:59 PM · Pratik
IDU/ODU Pressure Testing
Done
26 Aug 2026, 10:48 PM · Pratik
1st RA Measurement Submitted by PE
Done
26 Oct 2026, 10:59 PM · Pratik
HS Material Delivery IDU
Done
26 Oct 2026, 10:59 PM · Pratik
HS Material Delivery ODU
Done
26 Oct 2026, 10:59 PM · Pratik
Indoor Installation
Done
26 Oct 2026, 10:59 PM · Pratik
odu unit installation
Done
02 Nov 2026, 11:46 PM · Pratik
Final Nitrogen Testing
Done
26 Aug 2026, 10:48 PM · Pratik
Underdake Insulation
Not required
03 Sep 2026, 11:57 PM · Pratik
Copper Piping Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Drain Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
IDU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
ODU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting
Done
26 Oct 2026, 10:59 PM · Pratik
Fresh Air - PVC PIPE / Duct
Done
12 Sep 2026, 10:49 PM · Pratik
Civil Opening
Done
26 Oct 2026, 10:59 PM · Pratik
LS Material Delivery
Done
02 Nov 2026, 11:46 PM · Pratik
Grill Installation
Done
17 Nov 2026, 12:51 AM · Pratik

Complete visit timeline

25 visits
17 Nov 2026, 12:51 AM
Pratik · PPR-2026-11-00409
Step updates
Grill Installation · Done
ActivityPanels installation done.
Tomorrow's plan-
02 Nov 2026, 11:46 PM
Pratik · PPR-2026-11-00380
Step updates
LS Material Delivery · Doneodu unit installation · Done
Activityodu unit installation completed today.
Tomorrow's plan-
31 Oct 2026, 11:25 PM
Pratik · PPR-2026-10-00373
ActivityNon VRV (Server Room) IDU installation completed.
Tomorrow's planSunday
30 Oct 2026, 09:28 PM
Pratik · PPR-2026-10-00367
ActivityInvoice collected from office - Ground floor, Server Room.
Image not available.
Tomorrow's plan-
29 Oct 2026, 11:33 PM
Pratik · PPR-2026-10-00365
ActivityODU shifting done.
Server room non VRV units received at site.
Tomorrow's planNon VRV units installation.
26 Oct 2026, 10:59 PM
Pratik · PPR-2026-10-00351
Step updates
Marking · DoneSupport · DoneCivil Opening · DoneCopper Piping · DoneDrain · DoneCable · DoneLS Pressure Testing · DoneMain Ducting · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Done
ActivityIDU connection done
Tomorrow's planIDU connection
06 Oct 2026, 11:33 PM
Pratik · PPR-2026-10-00291
Step updates
Indoor Installation · Done
Activity6 Indoor Installation completed today.
Tomorrow's plan-
24 Sep 2026, 09:32 PM
Pratik · PPR-2026-09-00247
ActivityHS delivery received at site.
Tomorrow's planHoliday
23 Sep 2026, 11:59 PM
Pratik · PPR-2026-09-00245
ActivityMeasurements report created today.
Tomorrow's plan-
22 Sep 2026, 11:06 PM
Pratik · PPR-2026-09-00241
ActivityIDU's and panels received at site.
Tomorrow's plan-
19 Sep 2026, 10:52 PM
Pratik · PPR-2026-09-00235
Step updates
HS Material Delivery IDU · Done
ActivityHS Material Delivery IDU completed today.
FXZQ32CRV16 - 01 No
FXAQ50ARVE6 - 01 No
Received at site.
Tomorrow's planSunday
16 Sep 2026, 11:29 PM
Pratik · PPR-2026-09-00227
ActivityCable tray cutting for fresh air pipe.
Tomorrow's plan-
12 Sep 2026, 10:49 PM
Pratik · PPR-2026-09-00220
Step updates
Fresh Air - PVC PIPE / Duct · Done
ActivityFresh Air - PVC PIPE / Duct for 3 IDU's completed today.
Tomorrow's planSunday
11 Sep 2026, 11:41 PM
Pratik · PPR-2026-09-00216
ActivityMaterial delivered at site.
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct.
09 Sep 2026, 09:03 PM
Pratik · PPR-2026-09-00210
ActivityRemaining cable tray installation.
Tomorrow's plan-
05 Sep 2026, 11:49 PM
Pratik · PPR-2026-09-00202
ActivityRemaining copper piping.
Tomorrow's planSunday
04 Sep 2026, 11:25 PM
Pratik · PPR-2026-09-00199
Step updates
Main Ducting · Done
ActivityMain Ducting completed today.
Tomorrow's plan-
03 Sep 2026, 11:57 PM
Pratik · PPR-2026-09-00194
Step updates
Underdake Insulation · Not requiredCopper Piping Dismental · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not required
ActivityLS pressure testing done.
Tomorrow's plan-
29 Aug 2026, 10:21 PM
Pratik · PPR-2026-08-00173
ActivitySupporting for copper piping in shaft.
Tomorrow's planSunday
26 Aug 2026, 10:48 PM
Pratik · PPR-2026-08-00160
Step updates
Copper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Doneodu unit installation · DoneFinal Nitrogen Testing · Done
ActivityMaterial received at site.
Tomorrow's planCopper piping.
19 Aug 2026, 08:07 PM
Pratik · PPR-2026-08-00139
ActivityCopper piping for 10 indoor units done.
Tomorrow's planPlanned for tomorrow: Copper Piping.
19 Aug 2026, 12:13 AM
Pratik · PPR-2026-08-00132
ActivityCopper piping for 2 indoor units.
Tomorrow's planCopper piping.
12 Aug 2026, 06:52 PM
Pratik · PPR-2026-08-00103
Step updates
Support · Done
ActivitySupport completed today for 10 indoor units.
Tomorrow's planPlanned for tomorrow: Copper Piping. · starts 13 Aug 2026
11 Aug 2026, 09:56 PM
Pratik · PPR-2026-08-00101
Step updates
Marking · Done
ActivityMarking completed today.
Tomorrow's planPlanned for tomorrow: Support. · starts 12 Aug 2026
10 Aug 2026, 10:45 PM
Pratik · PPR-2026-08-00092
ActivityMeeting with contractor completed. Showed him complete site and discussed work.
Tomorrow's plan-

Photos and files

3 attachments

Report processing

done
photo save
done
29 Oct 2026, 11:33 PM
2 photo(s) uploaded
sheet write
done
29 Oct 2026, 11:33 PM
1 row(s) written
pms update
done
29 Oct 2026, 11:33 PM
PMS row stamped — 3 cell(s)
pdf
done
29 Oct 2026, 11:33 PM
PDF built
email
skipped
29 Oct 2026, 11:37 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
29 Oct 2026, 11:37 PM
Other Activity visit — report kept in-house, not sent to the client.