GAURAV ICON TOWER (7th floor)

PPR-2026-10-00343 · 24 Oct 2026, 10:39 PM
Open
EngineerNagraj
Site typeVRV · General
People on site2
ActivityFinal Nitrogen pressure testing in progress
Tomorrow's planPlanned for tomorrow: Pre-Commissioning.
Next step date—

Current project steps

6 tracked
Marking
Open
09 Oct 2026, 11:07 PM · Nagraj
Fresh Air - PVC PIPE / Duct
Open
09 Oct 2026, 11:07 PM · Nagraj
Indoor Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Fan Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Disk Valve
Open
24 Oct 2026, 10:39 PM · Nagraj
Final Nitrogen Testing
Open
24 Oct 2026, 10:39 PM · Nagraj

Complete visit timeline

6 visits
24 Oct 2026, 10:39 PM
Nagraj · PPR-2026-10-00343
Step updates
Disk Valve · OpenFinal Nitrogen Testing · Open
ActivityFinal Nitrogen pressure testing in progress
Tomorrow's planPlanned for tomorrow: Pre-Commissioning.
17 Oct 2026, 11:25 PM
Nagraj · PPR-2026-10-00328
Step updates
Indoor Installation · OpenFan Installation · Open
ActivityReception area machine installation done.

6nos machines copper piping and drain piping work completed

Split ac installation done.

1no fresh air fan installation done
Tomorrow's planPlanned for tomorrow: odu unit installation.
16 Oct 2026, 09:51 PM
Nagraj · PPR-2026-10-00324
Step updates
Indoor Installation · Open
Activity5nos indoor units installation done
Copper piping and drain piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation. No · starts 17 Oct 2026
14 Oct 2026, 11:18 PM
Pratik · PPR-2026-10-00318
Activity2 Nos - Split IDU and ODU received at site today.
Tomorrow's plan-
10 Oct 2026, 06:55 PM
Nagraj · PPR-2026-10-00305
Step updates
Indoor Installation · Open
ActivityIndoor units installation started
Tomorrow's planPlanned for tomorrow: Indoor Installation, Copper Piping, Drain. Indoor units installation
Copper pipe connection
Drain pipe connection · starts 12 Oct 2026
09 Oct 2026, 11:07 PM
Nagraj · PPR-2026-10-00303
Step updates
Marking · OpenFresh Air - PVC PIPE / Duct · Open
ActivityAll idu marking done

6nos machines rod fixing done

Fresh PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, Fresh Air - PVC PIPE / Duct, Drain. · starts 10 Oct 2026

Photos and files

10 attachments

Report processing

partial
photo save
done
24 Oct 2026, 10:40 PM
9 photo(s) uploaded
sheet write
done
24 Oct 2026, 10:40 PM
1 row(s) written
pms update
done
24 Oct 2026, 10:41 PM
PMS row stamped — 5 cell(s)
pdf
done
24 Oct 2026, 10:41 PM
PDF built
email
failed
24 Oct 2026, 10:49 PM
SMTP expected 250, got: 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp Transcript: < 220 smtp.gmail.com ESMTP a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-STARTTLS 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250 SMTPUTF8 > STARTTLS < 220 2.0.0 Ready to start TLS > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-AUTH LOGIN PLAIN XOAUTH2 PLAIN-CLIENTTOKEN OAUTHBEARER XOAUTH 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250 SMTPUTF8 > AUTH LOGIN < 334 VXNlcm5hbWU6 > Y3JtQHZha2hhcmlhYWlydGVjaC5jb20= < 334 UGFzc3dvcmQ6 > amt5byBiemppIGNycmQgc2RodA== < 235 2.7.0 Accepted > MAIL FROM:<crm@vakhariaairtech.com> < 250 2.1.0 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > RCPT TO:<purchase@gauraviconinfratech.com> < 250 2.1.5 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > RCPT TO:<vishal.bhavsar@dpplpro.com> < 250 2.1.5 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > RCPT TO:<gaurav.patil1@jll.com> < 250 2.1.5 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > RCPT TO:<crm@vakhariaairtech.com> < 250 2.1.5 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > RCPT TO:<piyush@vakhariaairtech.com> < 250 2.1.5 OK a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > DATA < 354 Go ahead a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp > Date: Sat, 24 Oct 2026 22:45:09 +0530 From: CRM Vakharia Airtech <crm@vakhariaairtech.com> To: purchase@gauraviconinfr… < 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError a92af1059eb24-198a1bfaebfsm8780733c88.15 - gsmtp (to purchase@gauraviconinfratech.com,vishal.bhavsar@dpplpro.com,gaurav.patil1@jll.com)
whatsapp
done
24 Oct 2026, 10:49 PM
SENT — doc media=28784821491144180