Ultra Unit - 6 Production Office (Ground Floor)

PPR-2026-10-00373 · 31 Oct 2026, 11:25 PM
—
EngineerPratik
Site typeVRV · General
People on site2
ActivityNon VRV (Server Room) IDU installation completed.
Tomorrow's planSunday
Next step date—

Current project steps

24 tracked
Marking
Done
26 Oct 2026, 10:59 PM · Pratik
Support
Done
26 Oct 2026, 10:59 PM · Pratik
Copper Piping
Done
26 Oct 2026, 10:59 PM · Pratik
Cable
Done
26 Oct 2026, 10:59 PM · Pratik
Drain
Done
26 Oct 2026, 10:59 PM · Pratik
LS Pressure Testing
Done
26 Oct 2026, 10:59 PM · Pratik
IDU/ODU Pressure Testing
Done
26 Aug 2026, 10:48 PM · Pratik
1st RA Measurement Submitted by PE
Done
26 Oct 2026, 10:59 PM · Pratik
HS Material Delivery IDU
Done
26 Oct 2026, 10:59 PM · Pratik
HS Material Delivery ODU
Done
26 Oct 2026, 10:59 PM · Pratik
Indoor Installation
Done
26 Oct 2026, 10:59 PM · Pratik
odu unit installation
Done
02 Nov 2026, 11:46 PM · Pratik
Final Nitrogen Testing
Done
26 Aug 2026, 10:48 PM · Pratik
Underdake Insulation
Not required
03 Sep 2026, 11:57 PM · Pratik
Copper Piping Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Drain Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
IDU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
ODU Dismental
Not required
03 Sep 2026, 11:57 PM · Pratik
Main Ducting
Done
26 Oct 2026, 10:59 PM · Pratik
Fresh Air - PVC PIPE / Duct
Done
12 Sep 2026, 10:49 PM · Pratik
Civil Opening
Done
26 Oct 2026, 10:59 PM · Pratik
LS Material Delivery
Done
02 Nov 2026, 11:46 PM · Pratik
Grill Installation
Done
17 Nov 2026, 12:51 AM · Pratik

Complete visit timeline

25 visits
17 Nov 2026, 12:51 AM
Pratik · PPR-2026-11-00409
Step updates
Grill Installation · Done
ActivityPanels installation done.
Tomorrow's plan-
02 Nov 2026, 11:46 PM
Pratik · PPR-2026-11-00380
Step updates
LS Material Delivery · Doneodu unit installation · Done
Activityodu unit installation completed today.
Tomorrow's plan-
31 Oct 2026, 11:25 PM
Pratik · PPR-2026-10-00373
ActivityNon VRV (Server Room) IDU installation completed.
Tomorrow's planSunday
30 Oct 2026, 09:28 PM
Pratik · PPR-2026-10-00367
ActivityInvoice collected from office - Ground floor, Server Room.
Image not available.
Tomorrow's plan-
29 Oct 2026, 11:33 PM
Pratik · PPR-2026-10-00365
ActivityODU shifting done.
Server room non VRV units received at site.
Tomorrow's planNon VRV units installation.
26 Oct 2026, 10:59 PM
Pratik · PPR-2026-10-00351
Step updates
Marking · DoneSupport · DoneCivil Opening · DoneCopper Piping · DoneDrain · DoneCable · DoneLS Pressure Testing · DoneMain Ducting · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Done
ActivityIDU connection done
Tomorrow's planIDU connection
06 Oct 2026, 11:33 PM
Pratik · PPR-2026-10-00291
Step updates
Indoor Installation · Done
Activity6 Indoor Installation completed today.
Tomorrow's plan-
24 Sep 2026, 09:32 PM
Pratik · PPR-2026-09-00247
ActivityHS delivery received at site.
Tomorrow's planHoliday
23 Sep 2026, 11:59 PM
Pratik · PPR-2026-09-00245
ActivityMeasurements report created today.
Tomorrow's plan-
22 Sep 2026, 11:06 PM
Pratik · PPR-2026-09-00241
ActivityIDU's and panels received at site.
Tomorrow's plan-
19 Sep 2026, 10:52 PM
Pratik · PPR-2026-09-00235
Step updates
HS Material Delivery IDU · Done
ActivityHS Material Delivery IDU completed today.
FXZQ32CRV16 - 01 No
FXAQ50ARVE6 - 01 No
Received at site.
Tomorrow's planSunday
16 Sep 2026, 11:29 PM
Pratik · PPR-2026-09-00227
ActivityCable tray cutting for fresh air pipe.
Tomorrow's plan-
12 Sep 2026, 10:49 PM
Pratik · PPR-2026-09-00220
Step updates
Fresh Air - PVC PIPE / Duct · Done
ActivityFresh Air - PVC PIPE / Duct for 3 IDU's completed today.
Tomorrow's planSunday
11 Sep 2026, 11:41 PM
Pratik · PPR-2026-09-00216
ActivityMaterial delivered at site.
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct.
09 Sep 2026, 09:03 PM
Pratik · PPR-2026-09-00210
ActivityRemaining cable tray installation.
Tomorrow's plan-
05 Sep 2026, 11:49 PM
Pratik · PPR-2026-09-00202
ActivityRemaining copper piping.
Tomorrow's planSunday
04 Sep 2026, 11:25 PM
Pratik · PPR-2026-09-00199
Step updates
Main Ducting · Done
ActivityMain Ducting completed today.
Tomorrow's plan-
03 Sep 2026, 11:57 PM
Pratik · PPR-2026-09-00194
Step updates
Underdake Insulation · Not requiredCopper Piping Dismental · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not required
ActivityLS pressure testing done.
Tomorrow's plan-
29 Aug 2026, 10:21 PM
Pratik · PPR-2026-08-00173
ActivitySupporting for copper piping in shaft.
Tomorrow's planSunday
26 Aug 2026, 10:48 PM
Pratik · PPR-2026-08-00160
Step updates
Copper Piping · DoneCable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · Done1st RA Measurement Submitted by PE · DoneHS Material Delivery IDU · DoneHS Material Delivery ODU · DoneIndoor Installation · Doneodu unit installation · DoneFinal Nitrogen Testing · Done
ActivityMaterial received at site.
Tomorrow's planCopper piping.
19 Aug 2026, 08:07 PM
Pratik · PPR-2026-08-00139
ActivityCopper piping for 10 indoor units done.
Tomorrow's planPlanned for tomorrow: Copper Piping.
19 Aug 2026, 12:13 AM
Pratik · PPR-2026-08-00132
ActivityCopper piping for 2 indoor units.
Tomorrow's planCopper piping.
12 Aug 2026, 06:52 PM
Pratik · PPR-2026-08-00103
Step updates
Support · Done
ActivitySupport completed today for 10 indoor units.
Tomorrow's planPlanned for tomorrow: Copper Piping. · starts 13 Aug 2026
11 Aug 2026, 09:56 PM
Pratik · PPR-2026-08-00101
Step updates
Marking · Done
ActivityMarking completed today.
Tomorrow's planPlanned for tomorrow: Support. · starts 12 Aug 2026
10 Aug 2026, 10:45 PM
Pratik · PPR-2026-08-00092
ActivityMeeting with contractor completed. Showed him complete site and discussed work.
Tomorrow's plan-

Photos and files

2 attachments

Report processing

done
photo save
done
31 Oct 2026, 11:26 PM
1 photo(s) uploaded
sheet write
done
31 Oct 2026, 11:26 PM
1 row(s) written
pms update
done
31 Oct 2026, 11:26 PM
PMS row stamped — 3 cell(s)
pdf
done
31 Oct 2026, 11:26 PM
PDF built
email
skipped
31 Oct 2026, 11:30 PM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
31 Oct 2026, 11:30 PM
Other Activity visit — report kept in-house, not sent to the client.