3rd Floor Mantry Building

PPR-2026-11-00401 · 15 Nov 2026, 01:14 PM
Open
EngineerAkash S
Site typeVRV · General
People on site—
ActivityConversation done about window opening and shifting of odu .
Tomorrow's planPlanned for tomorrow: odu unit installation. Odu positioning
Next step date—

Current project steps

12 tracked
LS Material Delivery
Open
15 Nov 2026, 01:14 PM · Akash S
HS Material Delivery ODU
Done
02 Nov 2026, 05:05 PM · Kishor Nannaware
Marking
Done
06 Nov 2026, 05:22 PM · Kishor Nannaware
Support
Done
06 Nov 2026, 05:22 PM · Kishor Nannaware
Copper Piping
Open
16 Nov 2026, 06:48 PM · Akash S
Drain
Open
13 Nov 2026, 04:39 PM · Akash S
Cable
Open
13 Nov 2026, 04:39 PM · Akash S
Underdake Insulation
Not required
17 Nov 2026, 06:42 PM · Akash S
Drain Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
Main Ducting Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
IDU Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S
ODU Dismental
Not required
17 Nov 2026, 06:42 PM · Akash S

Complete visit timeline

8 visits
17 Nov 2026, 06:42 PM
Akash S · PPR-2026-11-00411
Step updates
Underdake Insulation · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not required
ActivityCommunication Cable wip ,
8 cassette ac recieved, 14 panels received
Tomorrow's planPlanned for tomorrow: Cable, odu unit installation.
16 Nov 2026, 06:48 PM
Akash S · PPR-2026-11-00406
Step updates
Copper Piping · Open
ActivityWindow dismantled for odu shifting .
Tomorrow's planPlanned for tomorrow: Copper Piping. Copper piping wip
15 Nov 2026, 01:14 PM
Akash S · PPR-2026-11-00401
Step updates
LS Material Delivery · Open
ActivityConversation done about window opening and shifting of odu .
Tomorrow's planPlanned for tomorrow: odu unit installation. Odu positioning
13 Nov 2026, 04:39 PM
Akash S · PPR-2026-11-00396
Step updates
Copper Piping · OpenDrain · OpenCable · Open
ActivityCopper piping wip
Tomorrow's planWaiting for material delivery
06 Nov 2026, 05:22 PM
Kishor Nannaware · PPR-2026-11-00394
Step updates
Marking · DoneSupport · Done
ActivityHalf area supporting completed.
Tomorrow's planSupporting of copper pipe
02 Nov 2026, 05:05 PM
Kishor Nannaware · PPR-2026-11-00376
Step updates
HS Material Delivery ODU · Done
Activity2 nos of ODU received at site
Tomorrow's planPlanned for tomorrow: Marking, Support.
31 Oct 2026, 06:54 PM
Kishor Nannaware · PPR-2026-10-00371
Step updates
LS Material Delivery · Done
ActivityLow side material delivered at site.
Tomorrow's planNo work Tommorow
29 Oct 2026, 04:57 PM
Dada · PPR-2026-10-00360
ActivityVendor visit and site clearance checking
Tomorrow's planPlanned for tomorrow: Civil Opening.

Photos and files

8 attachments

Report processing

partial
photo save
done
15 Nov 2026, 01:15 PM
7 photo(s) uploaded
sheet write
done
15 Nov 2026, 01:15 PM
1 row(s) written
pms update
done
15 Nov 2026, 01:15 PM
PMS row stamped — 3 cell(s)
pdf
done
15 Nov 2026, 01:15 PM
PDF built
email
failed
15 Nov 2026, 01:23 PM
SMTP expected 250, got: 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp Transcript: < 220 smtp.gmail.com ESMTP 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-STARTTLS 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250-SMTPUTF8 250 LIMITS MAILMAX=1000 RCPTMAX=100 > STARTTLS < 220 2.0.0 Ready to start TLS > EHLO pms-vm.asia-south1-c.c.vakos-project-module-dsu.internal < 250-smtp.gmail.com at your service, [35.234.208.82] 250-SIZE 35882577 250-8BITMIME 250-AUTH LOGIN PLAIN XOAUTH2 PLAIN-CLIENTTOKEN OAUTHBEARER XOAUTH 250-ENHANCEDSTATUSCODES 250-PIPELINING 250-CHUNKING 250-SMTPUTF8 250 LIMITS MAILMAX=1000 RCPTMAX=100 > AUTH LOGIN < 334 VXNlcm5hbWU6 > Y3JtQHZha2hhcmlhYWlydGVjaC5jb20= < 334 UGFzc3dvcmQ6 > amt5byBiemppIGNycmQgc2RodA== < 235 2.7.0 Accepted > MAIL FROM:<crm@vakhariaairtech.com> < 250 2.1.0 OK 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > RCPT TO:<elarcinterior@gmail.com> < 250 2.1.5 OK 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > RCPT TO:<crm@vakhariaairtech.com> < 250 2.1.5 OK 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > RCPT TO:<piyush@vakhariaairtech.com> < 250 2.1.5 OK 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > DATA < 354 Go ahead 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp > Date: Sun, 15 Nov 2026 13:19:12 +0530 From: CRM Vakharia Airtech <crm@vakhariaairtech.com> To: elarcinterior@gmail.com… < 552-5.3.4 Your message exceeded Google's message size limits. To view our 552-5.3.4 message size guidelines, go to 552 5.3.4 https://support.google.com/mail/?p=MaxSizeError 5a478bee46e88-379560f5e06sm30182461eec.19 - gsmtp (to elarcinterior@gmail.com)
whatsapp
done
15 Nov 2026, 01:23 PM
SENT — doc media=4699780843632930