GAURAV ICON TOWER (7th floor)

PPR-2026-10-00328 · 17 Oct 2026, 11:25 PM
Open
EngineerNagraj
Site typeVRV · General
People on site2
ActivityReception area machine installation done.

6nos machines copper piping and drain piping work completed

Split ac installation done.

1no fresh air fan installation done
Tomorrow's planPlanned for tomorrow: odu unit installation.
Next step date—

Current project steps

6 tracked
Marking
Open
09 Oct 2026, 11:07 PM · Nagraj
Fresh Air - PVC PIPE / Duct
Open
09 Oct 2026, 11:07 PM · Nagraj
Indoor Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Fan Installation
Open
17 Oct 2026, 11:25 PM · Nagraj
Disk Valve
Open
24 Oct 2026, 10:39 PM · Nagraj
Final Nitrogen Testing
Open
24 Oct 2026, 10:39 PM · Nagraj

Complete visit timeline

6 visits
24 Oct 2026, 10:39 PM
Nagraj · PPR-2026-10-00343
Step updates
Disk Valve · OpenFinal Nitrogen Testing · Open
ActivityFinal Nitrogen pressure testing in progress
Tomorrow's planPlanned for tomorrow: Pre-Commissioning.
17 Oct 2026, 11:25 PM
Nagraj · PPR-2026-10-00328
Step updates
Indoor Installation · OpenFan Installation · Open
ActivityReception area machine installation done.

6nos machines copper piping and drain piping work completed

Split ac installation done.

1no fresh air fan installation done
Tomorrow's planPlanned for tomorrow: odu unit installation.
16 Oct 2026, 09:51 PM
Nagraj · PPR-2026-10-00324
Step updates
Indoor Installation · Open
Activity5nos indoor units installation done
Copper piping and drain piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, odu unit installation. No · starts 17 Oct 2026
14 Oct 2026, 11:18 PM
Pratik · PPR-2026-10-00318
Activity2 Nos - Split IDU and ODU received at site today.
Tomorrow's plan-
10 Oct 2026, 06:55 PM
Nagraj · PPR-2026-10-00305
Step updates
Indoor Installation · Open
ActivityIndoor units installation started
Tomorrow's planPlanned for tomorrow: Indoor Installation, Copper Piping, Drain. Indoor units installation
Copper pipe connection
Drain pipe connection · starts 12 Oct 2026
09 Oct 2026, 11:07 PM
Nagraj · PPR-2026-10-00303
Step updates
Marking · OpenFresh Air - PVC PIPE / Duct · Open
ActivityAll idu marking done

6nos machines rod fixing done

Fresh PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Indoor Installation, Fresh Air - PVC PIPE / Duct, Drain. · starts 10 Oct 2026

Photos and files

7 attachments

Report processing

done
photo save
done
17 Oct 2026, 11:26 PM
6 photo(s) uploaded
sheet write
done
17 Oct 2026, 11:26 PM
1 row(s) written
pms update
done
17 Oct 2026, 11:26 PM
PMS row stamped — 5 cell(s)
pdf
done
17 Oct 2026, 11:26 PM
PDF built
email
done
17 Oct 2026, 11:30 PM
emailed
whatsapp
done
17 Oct 2026, 11:30 PM
SENT — doc media=1844848476695919