PMS
New report History
← Back to report history

Pankaj Runwal Residence

PPR-2026-11-00383 · 03 Nov 2026, 11:49 AM
—
EngineerDada
Site typeVRV · General
People on site—
ActivityMeeting attend at site with architect and Clint
Tomorrow's planNo plan
Next step date—

Current project steps

11 tracked
LS Material Delivery
Done
06 Aug 2026, 04:16 PM · Dada
IDU/ODU Pressure Testing
Done
14 Oct 2026, 03:31 PM · Dada
Final Nitrogen Testing
Done
14 Oct 2026, 03:31 PM · Dada
Grill Installation
Open
06 Aug 2026, 04:16 PM · Dada
Disk Valve
Open
06 Aug 2026, 04:16 PM · Dada
FINAL RA Measurement Received
Done
14 Oct 2026, 03:31 PM · Dada
Pre-Commissining
Open
06 Aug 2026, 04:16 PM · Dada
Commissining
Open
06 Aug 2026, 04:16 PM · Dada
HS Material Delivery ODU
Done
25 Aug 2026, 03:26 PM · Dada
HS Material Delivery IDU
Done
25 Aug 2026, 03:26 PM · Dada
odu unit installation
Done
14 Oct 2026, 03:31 PM · Dada

Complete visit timeline

9 visits
03 Nov 2026, 11:49 AM
Dada · PPR-2026-11-00383
ActivityMeeting attend at site with architect and Clint
Tomorrow's planNo plan
14 Oct 2026, 03:31 PM
Dada · PPR-2026-10-00316
Step updates
IDU/ODU Pressure Testing · Doneodu unit installation · DoneFinal Nitrogen Testing · DoneFINAL RA Measurement Received · Done
ActivityReturn material send to Store . Cable tray , Drain pipe Etc .

Also Electrical power supply still Not recived at site. As Per disscus with Pankaj Runwal sir Today.
Tomorrow's planNo plan
03 Sep 2026, 08:47 PM
Dada · PPR-2026-09-00190
Step updates
Final Nitrogen Testing · Done
ActivityFinal Nitrogen presure testing work.
Tomorrow's planNo plan
02 Sep 2026, 10:54 AM
Dada · PPR-2026-09-00183
Step updates
odu unit installation · Done
ActivityIndoor unit installation marking Done.
Tomorrow's planMeeting attend at site with Anil sir
27 Aug 2026, 03:02 PM
Dada · PPR-2026-08-00163
Step updates
odu unit installation · Done
ActivityOdu Unit installation work
Tomorrow's planNo Plan
26 Aug 2026, 05:30 PM
Dada · PPR-2026-08-00159
ActivityDucting collar installation done 1 st floor
Tomorrow's planOdu Unit shifting & Copper pipe conection work
25 Aug 2026, 03:26 PM
Dada · PPR-2026-08-00156
Step updates
HS Material Delivery ODU · DoneHS Material Delivery IDU · Done
ActivityWalk in wardrobe area Supply Duct collar Fabrication work
Tomorrow's planOdu Unit shifting & Ducting Collar installation.
13 Aug 2026, 07:12 PM
Dada · PPR-2026-08-00109
ActivitySite visit with Daikin Engg Mr Sachin Gunjal sir
Tomorrow's planNo plan
06 Aug 2026, 04:16 PM
Dada · PPR-2026-08-00066
Step updates
LS Material Delivery · DoneIDU/ODU Pressure Testing · OpenFinal Nitrogen Testing · OpenGrill Installation · OpenDisk Valve · OpenFINAL RA Measurement Received · OpenPre-Commissining · OpenCommissining · OpenHS Material Delivery ODU · Done
ActivityMeeting at Site With Anil Ranka Sir .
Tomorrow's planNo plan

Photos and files

3 attachments

Report processing

done
photo save
done
03 Nov 2026, 11:50 AM
2 photo(s) uploaded
sheet write
done
03 Nov 2026, 11:50 AM
1 row(s) written
pms update
done
03 Nov 2026, 11:50 AM
PMS row stamped — 3 cell(s)
pdf
done
03 Nov 2026, 11:50 AM
PDF built
email
skipped
03 Nov 2026, 11:54 AM
Other Activity visit — report kept in-house, not sent to the client.
whatsapp
skipped
03 Nov 2026, 11:54 AM
Other Activity visit — report kept in-house, not sent to the client.