PMS
New report History
← Back to report history

Suyog Navkar › Kalpa › 1402

PPR-2026-09-00221 · 12 Sep 2026, 10:51 PM
Done
EngineerPratik
Site typeVRV · Developer
People on site2
Activityodu unit installation as per customer completed today.
Tomorrow's planSunday
Next step date

Current project steps

1 tracked
odu unit installation
Done
12 Sep 2026, 10:51 PM · Pratik

Complete visit timeline

1 visit
12 Sep 2026, 10:51 PM
Pratik · PPR-2026-09-00221
Step updates
odu unit installation · Done
Activityodu unit installation as per customer completed today.
Tomorrow's planSunday

Photos and files

2 attachments

Report processing

done
photo save
done
12 Sep 2026, 10:52 PM
1 photo(s) uploaded across 1 flat(s)
sheet write
done
12 Sep 2026, 10:52 PM
1 row(s) written
pms update
done
12 Sep 2026, 10:52 PM
PMS row stamped
pdf
done
12 Sep 2026, 10:52 PM
PDF built
email
done
12 Sep 2026, 10:56 PM
emailed
whatsapp
done
12 Sep 2026, 10:56 PM
SENT — doc media=2236886543548755