PINNACLE INDUSTRIES LIMITED(Server Room, DXQ Room)

PPR-2026-09-00217 · 11 Sep 2026, 11:42 PM
Done
EngineerPratik
Site typeNon-VRV · General
People on site2
ActivityCommissining completed today.
Tomorrow's plan-
Next step date

Current project steps

23 tracked
HS Material Delivery IDU
Done
29 Aug 2026, 10:18 PM · Pratik
HS Material Delivery ODU
Done
29 Aug 2026, 10:18 PM · Pratik
LS Material Delivery
Done
29 Aug 2026, 10:18 PM · Pratik
Main Ducting Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Main Ducting
Not required
02 Sep 2026, 11:41 PM · Pratik
Drain Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Copper Piping Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Underdake Insulation
Not required
02 Sep 2026, 11:41 PM · Pratik
Collar
Not required
02 Sep 2026, 11:41 PM · Pratik
IDU Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
ODU Dismental
Not required
02 Sep 2026, 11:41 PM · Pratik
Fan Installation
Not required
02 Sep 2026, 11:41 PM · Pratik
Disk Valve
Not required
02 Sep 2026, 11:41 PM · Pratik
Support
Done
02 Sep 2026, 11:41 PM · Pratik
Copper Piping
Done
03 Sep 2026, 11:53 PM · Pratik
Indoor Installation
Done
07 Sep 2026, 11:51 PM · Pratik
odu unit installation
Done
07 Sep 2026, 11:51 PM · Pratik
Cable
Done
11 Sep 2026, 11:42 PM · Pratik
Drain
Done
11 Sep 2026, 11:42 PM · Pratik
LS Pressure Testing
Done
11 Sep 2026, 11:42 PM · Pratik
IDU/ODU Pressure Testing
Done
11 Sep 2026, 11:42 PM · Pratik
Final Nitrogen Testing
Done
11 Sep 2026, 11:42 PM · Pratik
Commissining
Done
11 Sep 2026, 11:42 PM · Pratik

Complete visit timeline

7 visits
12 Sep 2026, 10:53 PM
Pratik · PPR-2026-09-00222
ActivityCasing patti for IDU installation completed today. Drain connection completed.
Tomorrow's planSunday
11 Sep 2026, 11:42 PM
Pratik · PPR-2026-09-00217
Step updates
Cable · DoneDrain · DoneLS Pressure Testing · DoneIDU/ODU Pressure Testing · DoneFinal Nitrogen Testing · DoneCommissining · Done
ActivityCommissining completed today.
Tomorrow's plan-
07 Sep 2026, 11:51 PM
Pratik · PPR-2026-09-00203
Step updates
Indoor Installation · Doneodu unit installation · Done
ActivityIndoor Installation completed today. odu unit installation completed today.
Tomorrow's plan-
04 Sep 2026, 11:28 PM
Pratik · PPR-2026-09-00201
ActivitySupporting for IDU installation
Tomorrow's planPlanned for tomorrow: Indoor Installation. · starts 05 Sep 2026
03 Sep 2026, 11:53 PM
Pratik · PPR-2026-09-00192
Step updates
Copper Piping · Done
ActivityCopper Piping completed today.
Tomorrow's planFabrication
02 Sep 2026, 11:41 PM
Pratik · PPR-2026-09-00189
Step updates
Main Ducting Dismental · Not requiredMain Ducting · Not requiredDrain Dismental · Not requiredCopper Piping Dismental · Not requiredUnderdake Insulation · Not requiredCollar · Not requiredIDU Dismental · Not requiredODU Dismental · Not requiredFan Installation · Not requiredDisk Valve · Not requiredSupport · Done
ActivitySupport completed today.
Tomorrow's planPlanned for tomorrow: Copper Piping.
29 Aug 2026, 10:18 PM
Pratik · PPR-2026-08-00172
Step updates
HS Material Delivery IDU · DoneHS Material Delivery ODU · DoneLS Material Delivery · Done
ActivityHS Material Delivery ODU completed today. HS Material Delivery IDU completed today. LS Material Delivery completed today.
Tomorrow's planSunday.

Photos and files

5 attachments

Report processing

done
photo save
done
11 Sep 2026, 11:43 PM
4 photo(s) uploaded
sheet write
done
11 Sep 2026, 11:43 PM
1 row(s) written
pms update
done
11 Sep 2026, 11:43 PM
PMS row stamped