02 Sep 2026, 11:38 PM
Pratik · PPR-2026-09-00188
Step updates
Drain Dismental · Not requiredMain Ducting Dismental · Not requiredCopper Piping Dismental · Not requiredIDU Dismental · Not requiredODU Dismental · Not requiredodu unit installation · Done
ActivityAll indoor communication wiring done.
Main power supply wiring done.
Grill fitting done.
Outdoor pressure hold.
Vacuuming and valve break done.
Auto charging and testing work pending
Because there is 40A + 30MA LMCB
Required 25A +300MA LMCB
Even earthing is not provided.
Main power supply wiring done.
Grill fitting done.
Outdoor pressure hold.
Vacuuming and valve break done.
Auto charging and testing work pending
Because there is 40A + 30MA LMCB
Required 25A +300MA LMCB
Even earthing is not provided.
Tomorrow's plan-