Samsung Office Baramati

PPR-2026-11-00385 · 03 Nov 2026, 02:47 PM
Done
EngineerAkash S
Site typeVRV · General
People on site—
Activity2 idu received ,
Tomorrow's planWaiting for material delivery
Next step date—

Current project steps

18 tracked
LS Material Delivery
Done
03 Nov 2026, 02:47 PM · Akash S
Marking
Done
29 Oct 2026, 10:23 AM · Akash S
Civil Opening
Done
29 Oct 2026, 10:23 AM · Akash S
Copper Piping
Done
30 Oct 2026, 10:12 PM · Akash S
LS Pressure Testing
Done
31 Oct 2026, 03:33 PM · Akash S
Cable
Done
03 Nov 2026, 02:47 PM · Akash S
Drain
Done
03 Nov 2026, 02:47 PM · Akash S
Underdake Insulation
Not required
03 Nov 2026, 02:47 PM · Akash S
Copper Piping Dismental
Not required
03 Nov 2026, 02:47 PM · Akash S
Drain Dismental
Not required
03 Nov 2026, 02:47 PM · Akash S
Main Ducting Dismental
Not required
03 Nov 2026, 02:47 PM · Akash S
Fresh Air - PVC PIPE / Duct
Not required
03 Nov 2026, 02:47 PM · Akash S
IDU Dismental
Not required
03 Nov 2026, 02:47 PM · Akash S
ODU Dismental
Not required
03 Nov 2026, 02:47 PM · Akash S
Grill Installation
Not required
03 Nov 2026, 02:47 PM · Akash S
Collar
Not required
03 Nov 2026, 02:47 PM · Akash S
Main Ducting
Not required
03 Nov 2026, 02:47 PM · Akash S
Support
Done
03 Nov 2026, 02:47 PM · Akash S

Complete visit timeline

6 visits
03 Nov 2026, 02:47 PM
Akash S · PPR-2026-11-00385
Step updates
LS Material Delivery · DoneCable · DoneDrain · DoneUnderdake Insulation · Not requiredCopper Piping Dismental · Not requiredDrain Dismental · Not requiredMain Ducting Dismental · Not requiredFresh Air - PVC PIPE / Duct · Not requiredIDU Dismental · Not requiredODU Dismental · Not requiredGrill Installation · Not requiredCollar · Not requiredMain Ducting · Not requiredSupport · Done
Activity2 idu received ,
Tomorrow's planWaiting for material delivery
31 Oct 2026, 03:33 PM
Akash S · PPR-2026-10-00370
Step updates
LS Pressure Testing · Done
ActivityRefnet insulation done .
Measurements taken
Tomorrow's planWaiting material delivery
30 Oct 2026, 10:12 PM
Akash S · PPR-2026-10-00368
Step updates
Copper Piping · Done
ActivityBreazing
Tomorrow's planRefnet insulation
29 Oct 2026, 10:23 AM
Akash S · PPR-2026-10-00359
Step updates
Marking · DoneCivil Opening · Done
ActivityCore cutting done , marking done , copper piping wip
Tomorrow's planPlanned for tomorrow: Drain. Copper piping breazing
27 Oct 2026, 05:42 PM
Akash S · PPR-2026-10-00354
Step updates
LS Material Delivery · Done
ActivitySupporting for copper piping
Tomorrow's planPlanned for tomorrow: Civil Opening. Core cutting
22 Oct 2026, 11:57 AM
Akash S · PPR-2026-10-00334
Step updates
LS Material Delivery · OpenMarking · Open
ActivityLock and key available.
Tomorrow's planPlanned for tomorrow: Marking. Waiting for material delivery

Photos and files

9 attachments

Report processing

done
photo save
done
03 Nov 2026, 02:49 PM
8 photo(s) uploaded
sheet write
done
03 Nov 2026, 02:49 PM
1 row(s) written
pms update
done
03 Nov 2026, 02:50 PM
PMS row stamped — 20 cell(s)
pdf
done
03 Nov 2026, 02:50 PM
PDF built
email
done
03 Nov 2026, 02:57 PM
emailed
whatsapp
done
03 Nov 2026, 02:57 PM
SENT — doc media=29141861402113929