DITTO SPACES LLP - STAR ENGINEERS INDIA PVT. LTD

PPR-2026-11-00392 · 05 Nov 2026, 09:16 PM
Open
EngineerNagraj
Site typeNon-VRV · General
People on site2
ActivityMain line ducting installation in progress
Tomorrow's planPlanned for tomorrow: Main Ducting. Nothing
Next step date31 Dec 2026

Current project steps

2 tracked
Support
Open
05 Nov 2026, 09:16 PM · Nagraj
Main Ducting
Open
05 Nov 2026, 09:16 PM · Nagraj

Complete visit timeline

2 visits
05 Nov 2026, 09:16 PM
Nagraj · PPR-2026-11-00392
Step updates
Support · OpenMain Ducting · Open
ActivityMain line ducting installation in progress
Tomorrow's planPlanned for tomorrow: Main Ducting. Nothing · starts 31 Dec 2026
09 Oct 2026, 01:26 AM
Pratik · PPR-2026-10-00299
ActivitySite visit for measurements.
Tomorrow's plan-

Photos and files

13 attachments

Report processing

partial
photo save
done
05 Nov 2026, 09:17 PM
12 photo(s) uploaded
sheet write
done
05 Nov 2026, 09:17 PM
1 row(s) written
pms update
done
05 Nov 2026, 09:17 PM
PMS row stamped — 6 cell(s)
pdf
done
05 Nov 2026, 09:18 PM
PDF built
email
done
05 Nov 2026, 09:24 PM
emailed
whatsapp
failed
05 Nov 2026, 09:24 PM
no client number