Rachana Developer - Kalbhor Residence

PPR-2026-09-00215 · 11 Sep 2026, 09:34 PM
Open
EngineerNagraj
Site typeVRV · General
People on site2
Activity12nos indoor units mouth connection done

Toilet pvc piping work in progress
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. Toilet ventilation PVC piping work will be continued
Next step date12 Sep 2026

Current project steps

5 tracked
Support
Open
01 Aug 2026, 09:30 PM · Nagraj
Marking
Open
12 Aug 2026, 08:10 PM · Nagraj
Collar
Open
01 Aug 2026, 09:30 PM · Nagraj
Indoor Installation
Open
04 Sep 2026, 08:19 PM · Nagraj
Fresh Air - PVC PIPE / Duct
Open
17 Sep 2026, 09:16 PM · Nagraj

Complete visit timeline

9 visits
17 Sep 2026, 09:16 PM
Nagraj · PPR-2026-09-00230
Step updates
Fresh Air - PVC PIPE / Duct · Open
ActivityToilet ventilation PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. Nothing · starts 18 Sep 2026
11 Sep 2026, 09:34 PM
Nagraj · PPR-2026-09-00215
Step updates
Fresh Air - PVC PIPE / Duct · Open
Activity12nos indoor units mouth connection done

Toilet pvc piping work in progress
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. Toilet ventilation PVC piping work will be continued · starts 12 Sep 2026
04 Sep 2026, 08:19 PM
Nagraj · PPR-2026-09-00195
Step updates
Indoor Installation · Open
Activity7nos indoors hanging done
Tomorrow's planPlanned for tomorrow: Indoor Installation. Nothing · starts 05 Sep 2026
12 Aug 2026, 08:10 PM
Nagraj · PPR-2026-08-00106
Step updates
Marking · Open
ActivityCopper piping work in progress
Tomorrow's planPlanned for tomorrow: Marking. Nothing · starts 14 Aug 2026
01 Aug 2026, 09:30 PM
Nagraj · PPR-2026-08-00051
Step updates
Marking · OpenSupport · OpenCollar · Open
ActivityRevised core cut marking done
Collar work in progress
Tomorrow's planPlanned for tomorrow: Collar.
31 Jul 2026, 09:59 AM
Prathamesh Paigude · PPR-2026-07-00043
Step updates
Support · Open
ActivitySupportfor lower Ground floor 50% completed
Tomorrow's planPlanned for tomorrow: Support. Remaining Support for lower ground floor will be completed · starts 31 Jul 2026
30 Jul 2026, 08:37 PM
Nagraj · PPR-2026-07-00040
Step updates
Support · Open
ActivityCore cutting work will be done tomorrow
Tomorrow's planPlanned for tomorrow: Copper Piping, Collar. Ducting collars will be fixed tomorrow · starts 31 Jul 2026
29 Jul 2026, 06:23 PM
Prathamesh Paigude · PPR-2026-07-00031
Step updates
Support · Open
ActivitySupport for - First Floor and Ground Floor completed.
Tomorrow's planPlanned for tomorrow: Support. Support for Lower Ground Floor will be done tomorrow · starts 30 Jul 2026
28 Jul 2026, 06:38 PM
Prathamesh Paigude · PPR-2026-07-00017
Step updates
Support · Open
ActivityFirst Floor- Support Completed
Ground Floor- Pending
Tomorrow's planPlanned for tomorrow: Support. Ground Floor- Support will be done · starts 29 Jul 2026

Photos and files

10 attachments

Report processing

done
photo save
done
11 Sep 2026, 09:35 PM
9 photo(s) uploaded
sheet write
done
11 Sep 2026, 09:35 PM
1 row(s) written
pms update
done
11 Sep 2026, 09:35 PM
PMS row stamped
pdf
done
11 Sep 2026, 09:35 PM
PDF built
email
done
11 Sep 2026, 09:39 PM
emailed
whatsapp
done
11 Sep 2026, 09:39 PM
SENT — doc media=1722063882431575