LS Material Delivery
Done
19 Aug 2026, 07:05 PM · Shubham
Marking
Done
19 Aug 2026, 07:05 PM · Shubham
Civil Opening
Done
19 Aug 2026, 07:05 PM · Shubham
Support
Done
19 Aug 2026, 07:05 PM · Shubham
Copper Piping
Done
19 Aug 2026, 07:05 PM · Shubham
Cable
Done
19 Aug 2026, 07:05 PM · Shubham
Drain
Done
19 Aug 2026, 07:05 PM · Shubham
LS Pressure Testing
Done
19 Aug 2026, 07:05 PM · Shubham
HS Material Delivery IDU
Done
19 Aug 2026, 07:05 PM · Shubham
HS Material Delivery ODU
Done
19 Aug 2026, 07:05 PM · Shubham
Indoor Installation
Done
19 Aug 2026, 07:05 PM · Shubham
odu unit installation
Done
19 Aug 2026, 07:05 PM · Shubham
Underdake Insulation
Not required
22 Oct 2026, 08:06 PM · Shubham
Copper Piping Dismental
Not required
22 Oct 2026, 08:06 PM · Shubham
Drain Dismental
Not required
22 Oct 2026, 08:06 PM · Shubham
Main Ducting
Not required
22 Oct 2026, 08:06 PM · Shubham
Main Ducting Dismental
Not required
22 Oct 2026, 08:06 PM · Shubham
Collar
Not required
22 Oct 2026, 08:06 PM · Shubham
1st RA Measurement Submitted by PE
Not required
22 Oct 2026, 08:06 PM · Shubham
IDU Dismental
Not required
22 Oct 2026, 08:06 PM · Shubham
ODU Dismental
Not required
22 Oct 2026, 08:06 PM · Shubham
Final Nitrogen Testing
Done
22 Oct 2026, 08:06 PM · Shubham