RENOLIT India Pvt. Ltd

PPR-2026-08-00152 · 24 Aug 2026, 06:52 PM
Open
EngineerNagraj
Site typeVRV · General
People on site3
ActivityCabling work in progress
2nos fresh air fan installation done
2nd floor drain piping work in progress
Tomorrow's planPlanned for tomorrow: Drain, Cable, Fan Installation. Nothing
Next step date25 Aug 2026

Current project steps

6 tracked
Drain
Open
08 Sep 2026, 07:13 PM · Nagraj
LS Pressure Testing
Open
08 Aug 2026, 07:54 PM · Nagraj
Fresh Air - PVC PIPE / Duct
Open
02 Sep 2026, 07:35 PM · Nagraj
Cable
Open
24 Aug 2026, 06:52 PM · Nagraj
Fan Installation
Open
02 Sep 2026, 07:35 PM · Nagraj
Indoor Installation
Open
16 Sep 2026, 10:13 PM · Nagraj

Complete visit timeline

10 visits
16 Sep 2026, 10:13 PM
Nagraj · PPR-2026-09-00226
Step updates
Indoor Installation · Open
ActivityTotal 13 nos indoor units copper and drain connections done
Tomorrow's planPlanned for tomorrow: Indoor Installation. Ground floor machines installation will be done if will get clearance, as there is painting pending · starts 18 Sep 2026
15 Sep 2026, 05:50 PM
Nagraj · PPR-2026-09-00223
Step updates
Indoor Installation · Open
Activity6nos hi-wall units and 3nos cassette AC installation done
Tomorrow's planPlanned for tomorrow: Indoor Installation. Indoor units connection will be done which is installed · starts 16 Sep 2026
08 Sep 2026, 07:13 PM
Nagraj · PPR-2026-09-00206
Step updates
Drain · OpenIndoor Installation · Open
ActivityAll hi-wall units drain piping work completed
All hi-wall units marking done for boxing
Reception area 1no Cassette AC installation done.
Fan mouth connection done.
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. · starts 09 Sep 2026
02 Sep 2026, 07:35 PM
Nagraj · PPR-2026-09-00185
Step updates
Drain · OpenFresh Air - PVC PIPE / Duct · OpenFan Installation · Open
ActivityGround and First Floor copper piping in progress in partition.

Fan installation work in progress

Outdoor unit received at site
Tomorrow's planPlanned for tomorrow: LS Pressure Testing, Fan Installation. · starts 03 Sep 2026
24 Aug 2026, 06:52 PM
Nagraj · PPR-2026-08-00152
Step updates
Cable · OpenDrain · OpenFan Installation · Open
ActivityCabling work in progress
2nos fresh air fan installation done
2nd floor drain piping work in progress
Tomorrow's planPlanned for tomorrow: Drain, Cable, Fan Installation. Nothing · starts 25 Aug 2026
21 Aug 2026, 09:06 PM
Nagraj · PPR-2026-08-00146
Step updates
Cable · Open
ActivityGround floor copper piping in progress
Tomorrow's planPlanned for tomorrow: Drain, Cable. Humidifier and Dehumidifier-marking · starts 22 Aug 2026
13 Aug 2026, 08:10 PM
Nagraj · PPR-2026-08-00113
Step updates
Fresh Air - PVC PIPE / Duct · Open
ActivityFlexible duct installation work in progress for fresh air and toilet PVC pipe

Core cutting work done for copper piping

Wall opening done for pvc piping
Tomorrow's planNo work has planned for tomorrow
12 Aug 2026, 08:05 PM
Nagraj · PPR-2026-08-00105
Step updates
Fresh Air - PVC PIPE / Duct · Open
ActivityGround floor toilet pvc piping work completed
1st floor fresh pvc piping work completed
2nd floor fresh air PVC piping work completed

Flexible duct and main fresh air PVC pipe towards shaft will be continued
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. Fresh Air PVC piping work will be continued.
Core cut for copper piping will be done tomorrow · starts 13 Aug 2026
11 Aug 2026, 08:01 PM
Nagraj · PPR-2026-08-00100
Step updates
Fresh Air - PVC PIPE / Duct · Open
ActivitySecond Floor - Fresh air and toilet pvc piping work completed

First Floor- Fresh air PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct. Fresh air and toilet pvc piping work will be continued · starts 12 Aug 2026
08 Aug 2026, 07:54 PM
Nagraj · PPR-2026-08-00086
Step updates
Drain · OpenLS Pressure Testing · Open
Activity1st floor and 2nd floor copper pipe brazing work completed...
2nd floor fresh air PVC piping work in progress
Tomorrow's planPlanned for tomorrow: Fresh Air - PVC PIPE / Duct, LS Pressure Testing. Toilet ventilation work willbe started · starts 11 Aug 2026

Photos and files

3 attachments

Report processing

done
photo save
done
24 Aug 2026, 06:53 PM
2 photo(s) uploaded
sheet write
done
24 Aug 2026, 06:53 PM
1 row(s) written
pms update
done
24 Aug 2026, 06:53 PM
PMS row stamped
pdf
done
24 Aug 2026, 06:53 PM
PDF built
email
done
24 Aug 2026, 06:57 PM
emailed
whatsapp
done
24 Aug 2026, 06:57 PM
SENT — doc media=3770736103073417